OVERPASS USING PC BRIDGE PIER WITH DOUBLE SHEAR REINFORCEMENT ARRANGEMENT
To provide an overpass which prevents the internal concrete from bulging out and collapsing, and which also prevents a main reinforcement from buckling to keep a bridge pier from breaking even when a large impact force acts in the vertical direction (axial direction of bridge pier member) during a large earthquake.SOLUTION: An overpass is formed of a foundation made of concrete, a bridge pier 3, a bridge girder 4, and a floor slab 5. The bridge piers are formed in columnar shapes, and the overpass is a PC bridge piers prestressed by tensioning and fixing PC steel arranged from the foundation to the full height (H) of the bridge pier. A double shear reinforcement bar 21 composed of an outer peripheral hoop reinforcement and a middle hoop reinforcement is disposed within a prescribed height range of the head and base of the PC pier. The middle hoop reinforcement is a spiral reinforcement. By placing the double shear reinforcement bars at the head and base of the prestressed PC bridge pier, the concrete surrounded by the spiral reinforcement used as the middle hoop becomes a center column. This is strongly restrained by the concrete further surrounded by the outer peripheral hoop reinforcement on the outer peripheral surface.SELECTED DRAWING: Figure 9
【課題】巨大地震時に、鉛直方向(橋脚部材の軸方向)に巨大な衝撃力が作用しても、内部のコンクリートが膨出圧壊されないようにすると共に、主筋も座屈しないようにし、橋脚が破損しない高架橋の提供。【解決手段】コンクリ—ト製の基礎と、橋脚3と、橋桁4及び床版5とで形成される高架橋であって、橋脚が柱状に形成され、基礎から橋脚の全高(H)に亘って配置されたPC鋼材を緊張定着することによりプレストレスが付与されたPC橋脚であり、PC橋脚の頭部と基部の所定高さ範囲内に外周フープ筋と、中フープ筋とで構成されてなる二重せん断補強筋21が配置され、中フープ筋をスパイラル筋とするものであり、プレストレスを付与したPC橋脚の頭部と基部に二重せん断補強筋を配置して形成されることにより、中フープとするスパイラル筋で囲まれたコンクリートが心柱になり、その外周面にさらに外周フープ筋で囲まれたコンクリートに強固に拘束される。【選択図】図9
OVERPASS USING PC BRIDGE PIER WITH DOUBLE SHEAR REINFORCEMENT ARRANGEMENT
To provide an overpass which prevents the internal concrete from bulging out and collapsing, and which also prevents a main reinforcement from buckling to keep a bridge pier from breaking even when a large impact force acts in the vertical direction (axial direction of bridge pier member) during a large earthquake.SOLUTION: An overpass is formed of a foundation made of concrete, a bridge pier 3, a bridge girder 4, and a floor slab 5. The bridge piers are formed in columnar shapes, and the overpass is a PC bridge piers prestressed by tensioning and fixing PC steel arranged from the foundation to the full height (H) of the bridge pier. A double shear reinforcement bar 21 composed of an outer peripheral hoop reinforcement and a middle hoop reinforcement is disposed within a prescribed height range of the head and base of the PC pier. The middle hoop reinforcement is a spiral reinforcement. By placing the double shear reinforcement bars at the head and base of the prestressed PC bridge pier, the concrete surrounded by the spiral reinforcement used as the middle hoop becomes a center column. This is strongly restrained by the concrete further surrounded by the outer peripheral hoop reinforcement on the outer peripheral surface.SELECTED DRAWING: Figure 9
【課題】巨大地震時に、鉛直方向(橋脚部材の軸方向)に巨大な衝撃力が作用しても、内部のコンクリートが膨出圧壊されないようにすると共に、主筋も座屈しないようにし、橋脚が破損しない高架橋の提供。【解決手段】コンクリ—ト製の基礎と、橋脚3と、橋桁4及び床版5とで形成される高架橋であって、橋脚が柱状に形成され、基礎から橋脚の全高(H)に亘って配置されたPC鋼材を緊張定着することによりプレストレスが付与されたPC橋脚であり、PC橋脚の頭部と基部の所定高さ範囲内に外周フープ筋と、中フープ筋とで構成されてなる二重せん断補強筋21が配置され、中フープ筋をスパイラル筋とするものであり、プレストレスを付与したPC橋脚の頭部と基部に二重せん断補強筋を配置して形成されることにより、中フープとするスパイラル筋で囲まれたコンクリートが心柱になり、その外周面にさらに外周フープ筋で囲まれたコンクリートに強固に拘束される。【選択図】図9
OVERPASS USING PC BRIDGE PIER WITH DOUBLE SHEAR REINFORCEMENT ARRANGEMENT
二重せん断補強筋が配置されたPC橋脚を用いた高架橋
KUROSAWA RYOHEI (Autor:in)
13.06.2019
Patent
Elektronische Ressource
Japanisch
IPC:
E01D
BRIDGES
,
Brücken
Overpass bridge pier backward movement transformation method
Europäisches Patentamt | 2024
|Dismantling method suitable for middle-pier-free overpass bridge
Europäisches Patentamt | 2023
|System for preventing vehicle from colliding with bridge pier of overpass bridge
Europäisches Patentamt | 2022
|