DECK SLAB CONSTRUCTION METHOD
To run an erection machine without applying the load of the erection machine on already erected deck slabs when the deck slabs are erected from near side and sequentially erected while moving forward.SOLUTION: At least above installed deck slabs 2A, 2B, rails 5 (5A, 5B) are built while a main girder 1 is made to support with no load applied on the deck slabs. The rails 5 are supported by a support leg 6 via the support leg 6 provided on the main girder 1 between adjacent front and rear deck slabs 2, and supported by a receiving beam 7 extending in a direction orthogonal to the main girder 1. An erection machine 10 which transports slabs 2C for erection moves forward on the rails 5 and installs the deck slabs 2C at deck slab installation positions X adjacent to the latest installed deck slabs 2B. Thereafter, the erection machine 10 moves backward on the rails 5 to receive the deck slabs for erection.SELECTED DRAWING: Figure 1
【課題】 床版を手前側から架設し、順次先方へ前進しつつ架設する場合に、設置済みの床版に架設機の荷重をかけることなく、架設機を走行させる。【解決手段】 少なくとも設置済みの床版2A、2Bの上方に、当該床版に荷重をかけることなく、主桁1に支持させて、レール5(5A、5B)を敷設する。レール5は、隣接する前後の床版2間において主桁1上に配置した支持脚6を介し、支持脚6により支持されて主桁1と直交する方向に延びる受梁7により支持する。設置用の床版2Cを運搬する架設機10は、レール5上を前進移動して、最新に設置された床版2Bに隣接する床版設置位置Xに、床版2Cを設置する。その後、架設機10は、設置用の床版の受取りのためにレール5上を後退移動する。【選択図】 図1
DECK SLAB CONSTRUCTION METHOD
To run an erection machine without applying the load of the erection machine on already erected deck slabs when the deck slabs are erected from near side and sequentially erected while moving forward.SOLUTION: At least above installed deck slabs 2A, 2B, rails 5 (5A, 5B) are built while a main girder 1 is made to support with no load applied on the deck slabs. The rails 5 are supported by a support leg 6 via the support leg 6 provided on the main girder 1 between adjacent front and rear deck slabs 2, and supported by a receiving beam 7 extending in a direction orthogonal to the main girder 1. An erection machine 10 which transports slabs 2C for erection moves forward on the rails 5 and installs the deck slabs 2C at deck slab installation positions X adjacent to the latest installed deck slabs 2B. Thereafter, the erection machine 10 moves backward on the rails 5 to receive the deck slabs for erection.SELECTED DRAWING: Figure 1
【課題】 床版を手前側から架設し、順次先方へ前進しつつ架設する場合に、設置済みの床版に架設機の荷重をかけることなく、架設機を走行させる。【解決手段】 少なくとも設置済みの床版2A、2Bの上方に、当該床版に荷重をかけることなく、主桁1に支持させて、レール5(5A、5B)を敷設する。レール5は、隣接する前後の床版2間において主桁1上に配置した支持脚6を介し、支持脚6により支持されて主桁1と直交する方向に延びる受梁7により支持する。設置用の床版2Cを運搬する架設機10は、レール5上を前進移動して、最新に設置された床版2Bに隣接する床版設置位置Xに、床版2Cを設置する。その後、架設機10は、設置用の床版の受取りのためにレール5上を後退移動する。【選択図】 図1
DECK SLAB CONSTRUCTION METHOD
床版架設方法
MIMURO KEIJI (Autor:in) / SAITO SHIGERU (Autor:in) / TAJIMA SHINICHI (Autor:in) / KOBAYASHI KATSUYA (Autor:in) / FUJIMOTO TATSUKI (Autor:in) / KAMEI YOSHIYUKI (Autor:in) / YAMANAKA HIROYUKI (Autor:in)
09.01.2020
Patent
Elektronische Ressource
Japanisch
IPC:
E01D
BRIDGES
,
Brücken
DECK SLAB, DECK SLAB CONSTRUCTION METHOD, AND DECK SLAB DESIGN METHOD
Europäisches Patentamt | 2023
|CONSTRUCTION METHOD OF BRIDGE DECK SLAB ASSEMBLY FOR BRIDGE DECK SLAB AND BRIDGE DECK SLAB
Europäisches Patentamt | 2018
|Construction method of bridge deck slab, bridge deck slab and bridge
Europäisches Patentamt | 2022
|