BOLTLESS METHOD OF STEEL FRAME ARCHITECTURAL STRUCTURE
To solve the problem in which although a method for manufacturing a column beam joint damper part at a factory and arranging a bolt joint using a high tension bolt at a position apart from an end of a beam for length of about 1 m is often used in a construction on site of the column beam structure of the steel frame architecture, an effective method for a steel frame construction without using the high tension bolt is needed and when a number of the bolts is used, a splice plate needs to be prepared for its joint part and drilling process for the bolts is needed, a number of man hour is needed.SOLUTION: When a structure of a column and a beam is assembled on site, the invention tights a row of temporary bolts 19 removable with a gusset welded to the column and a beam web 11 temporarily and applies fillet welding to the gusset and the beam web in longitudinal and transverse direction on construction site. By this a number of high tension bolts which is conventionally 10-100 per one joint can be saved and work man hour regarding the use of the bolts can be saved.SELECTED DRAWING: Figure 6
【課題】鉄骨建築の柱梁構造物の現場建て方を行う場合、柱梁仕口部を工場で製作し、梁の端部から長さ1m程度離れた位置でハイテンボルトを使ったボルト継手を設ける方法が良く用いられているが、高力(ハイテン)ボルトを使わない鉄骨建て方の効率的な方法が求められている。また、多数のボルトを使った場合にその継手部にスプライスプレートを用意し、且つボルト用の孔開け加工が必要になってくるため多くの工数が掛かる。【解決手段】本発明は、柱と梁の構造物を現場組み立てする場合に、柱に溶接接合されたガセットと梁ウエブ11とを取り外し可能な仮ボルト19を一列で仮締めし、ガセットと梁ウエブとを建設現場で縦方向と横方向すみ肉溶接する。このことで1継手当たり従来10〜100本の多数のハイテンボルトが省略され、ボルト使用に伴う作業工数が省ける。【選択図】図6
BOLTLESS METHOD OF STEEL FRAME ARCHITECTURAL STRUCTURE
To solve the problem in which although a method for manufacturing a column beam joint damper part at a factory and arranging a bolt joint using a high tension bolt at a position apart from an end of a beam for length of about 1 m is often used in a construction on site of the column beam structure of the steel frame architecture, an effective method for a steel frame construction without using the high tension bolt is needed and when a number of the bolts is used, a splice plate needs to be prepared for its joint part and drilling process for the bolts is needed, a number of man hour is needed.SOLUTION: When a structure of a column and a beam is assembled on site, the invention tights a row of temporary bolts 19 removable with a gusset welded to the column and a beam web 11 temporarily and applies fillet welding to the gusset and the beam web in longitudinal and transverse direction on construction site. By this a number of high tension bolts which is conventionally 10-100 per one joint can be saved and work man hour regarding the use of the bolts can be saved.SELECTED DRAWING: Figure 6
【課題】鉄骨建築の柱梁構造物の現場建て方を行う場合、柱梁仕口部を工場で製作し、梁の端部から長さ1m程度離れた位置でハイテンボルトを使ったボルト継手を設ける方法が良く用いられているが、高力(ハイテン)ボルトを使わない鉄骨建て方の効率的な方法が求められている。また、多数のボルトを使った場合にその継手部にスプライスプレートを用意し、且つボルト用の孔開け加工が必要になってくるため多くの工数が掛かる。【解決手段】本発明は、柱と梁の構造物を現場組み立てする場合に、柱に溶接接合されたガセットと梁ウエブ11とを取り外し可能な仮ボルト19を一列で仮締めし、ガセットと梁ウエブとを建設現場で縦方向と横方向すみ肉溶接する。このことで1継手当たり従来10〜100本の多数のハイテンボルトが省略され、ボルト使用に伴う作業工数が省ける。【選択図】図6
BOLTLESS METHOD OF STEEL FRAME ARCHITECTURAL STRUCTURE
鉄骨建築構造物のボルトレス工法