MACHINE WORKING PLATFORM AND ROOF CONSTRUCTION METHOD
To provide a machine working platform and a roof construction method, capable of efficiently disposing folded plates on a roof.SOLUTION: A molding machine M1 for molding folded plates to constitute a folded-plate roof from a steel plate roll is placed on a machine working platform 50. The machine working platform 50 includes: a movement mechanism comprising a TIRCLIMBER for moving a folded plate in an arrangement direction D1 and a travel unit 51; a lifting/lowering stage 66 for placement of the molding machine M1; and a chain block 65 for lifting/lowering the lifting/lowering stage 66. Depending on a position at which a folded plate is to be disposed, the machine working platform 50 performs position adjustment using the movement mechanism and a lifting/lowering mechanism.SELECTED DRAWING: Figure 19
【課題】折板を屋根に効率的に配置することができる機械構台及び屋根施工方法を提供する。【解決手段】機械構台50は、折板屋根を構成する折板を鋼板ロールから成形する成形機M1を載置する。機械構台50は、折板を並べる方向D1に移動させるチルクライマ及び走行部51を備える移動機構と、成形機M1を載置する昇降ステージ66と、昇降ステージ66を昇降するチェーンブロック65を有する。機械構台50は、折板が配置される位置に応じて、移動機構及び昇降機構により位置調節を行なう。【選択図】図19
MACHINE WORKING PLATFORM AND ROOF CONSTRUCTION METHOD
To provide a machine working platform and a roof construction method, capable of efficiently disposing folded plates on a roof.SOLUTION: A molding machine M1 for molding folded plates to constitute a folded-plate roof from a steel plate roll is placed on a machine working platform 50. The machine working platform 50 includes: a movement mechanism comprising a TIRCLIMBER for moving a folded plate in an arrangement direction D1 and a travel unit 51; a lifting/lowering stage 66 for placement of the molding machine M1; and a chain block 65 for lifting/lowering the lifting/lowering stage 66. Depending on a position at which a folded plate is to be disposed, the machine working platform 50 performs position adjustment using the movement mechanism and a lifting/lowering mechanism.SELECTED DRAWING: Figure 19
【課題】折板を屋根に効率的に配置することができる機械構台及び屋根施工方法を提供する。【解決手段】機械構台50は、折板屋根を構成する折板を鋼板ロールから成形する成形機M1を載置する。機械構台50は、折板を並べる方向D1に移動させるチルクライマ及び走行部51を備える移動機構と、成形機M1を載置する昇降ステージ66と、昇降ステージ66を昇降するチェーンブロック65を有する。機械構台50は、折板が配置される位置に応じて、移動機構及び昇降機構により位置調節を行なう。【選択図】図19
MACHINE WORKING PLATFORM AND ROOF CONSTRUCTION METHOD
機械構台及び屋根施工方法
MITSUNAGA YU (Autor:in) / UESHIMA YASUHIRO (Autor:in)
13.09.2021
Patent
Elektronische Ressource
Japanisch
IPC:
E04D
ROOF COVERINGS
,
Dacheindeckungen
Europäisches Patentamt | 2020
|Large slope roof construction platform manufacturing method
Europäisches Patentamt | 2021
|WORKING PLATFORM FOR MAINTAINING ATTACHMENT OF CONSTRUCTION MACHINE