HUMP CONSTRUCTION METHOD AND FORMWORK FOR HUMP CONSTRUCTION
To provide a hump construction method and a formwork for hump construction that enable humps with vertical curves to be constructed quickly and accurately.SOLUTION: In a hump construction method, a formwork 1 for both sides and an inner formwork 10 are used, pavement materials are spread between the formwork 1 for both sides and the inner formwork 10, a first layer is constructed by roll-pressing so that the surface of the pavement materials matches a first layer profile curve, which is similar to the hump profile, a second layer is constructed so that the surface of the pavement materials matches the profile curve of the hump provided in the upper part in the longitudinal direction of the inner formwork 10, and furthermore, on the second layer, the pavement materials are spread and roll-pressed, and a third layer is constructed by roll-pressing the surface so that the surface of the pavement materials matches the profile curve of the hump.SELECTED DRAWING: Figure 1
【課題】縦断曲線を有するハンプを、迅速且つ正確に施工することができるハンプ施工方法とその方法に使用するハンプ施工用型枠を提供する。【解決手段】このハンプ施工方法は、両側型枠1と内側型枠10を使用し、両側型枠1と内側型枠10との間に、舗装材料を撒き出し、ハンプの縦断曲線と類似する第1層縦断曲線と舗装材料の表面が一致するように転圧して第1層を施工し、さらに、第1層の上に、舗装材料を撒き出しながら転圧し、舗装材料の表面が内側型枠10の上部長手方向に設けたハンプの縦断曲線と一致するように第2層を施工し、さらに、第2層の上に、舗装材料を撒き出しながら転圧し、舗装材料の表面がハンプの縦断曲線と一致するように、表面を転圧して、第3層を施工する。【選択図】図1
HUMP CONSTRUCTION METHOD AND FORMWORK FOR HUMP CONSTRUCTION
To provide a hump construction method and a formwork for hump construction that enable humps with vertical curves to be constructed quickly and accurately.SOLUTION: In a hump construction method, a formwork 1 for both sides and an inner formwork 10 are used, pavement materials are spread between the formwork 1 for both sides and the inner formwork 10, a first layer is constructed by roll-pressing so that the surface of the pavement materials matches a first layer profile curve, which is similar to the hump profile, a second layer is constructed so that the surface of the pavement materials matches the profile curve of the hump provided in the upper part in the longitudinal direction of the inner formwork 10, and furthermore, on the second layer, the pavement materials are spread and roll-pressed, and a third layer is constructed by roll-pressing the surface so that the surface of the pavement materials matches the profile curve of the hump.SELECTED DRAWING: Figure 1
【課題】縦断曲線を有するハンプを、迅速且つ正確に施工することができるハンプ施工方法とその方法に使用するハンプ施工用型枠を提供する。【解決手段】このハンプ施工方法は、両側型枠1と内側型枠10を使用し、両側型枠1と内側型枠10との間に、舗装材料を撒き出し、ハンプの縦断曲線と類似する第1層縦断曲線と舗装材料の表面が一致するように転圧して第1層を施工し、さらに、第1層の上に、舗装材料を撒き出しながら転圧し、舗装材料の表面が内側型枠10の上部長手方向に設けたハンプの縦断曲線と一致するように第2層を施工し、さらに、第2層の上に、舗装材料を撒き出しながら転圧し、舗装材料の表面がハンプの縦断曲線と一致するように、表面を転圧して、第3層を施工する。【選択図】図1
HUMP CONSTRUCTION METHOD AND FORMWORK FOR HUMP CONSTRUCTION
ハンプ施工方法とハンプ施工用型枠
MIDORI AKIHIRO (Autor:in) / TANIGAWA EIJI (Autor:in) / TERAKURA YOSHIHIRO (Autor:in)
25.01.2022
Patent
Elektronische Ressource
Japanisch
IPC:
E01C
Bau von Straßen, Sportplätzen oder dgl., Decken dafür
,
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE
/
E01F
ADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
,
Zusätzliche Baumaßnahmen, wie die Ausstattung von Straßen oder die bauliche Ausbildung von Bahnsteigen, Landeplätzen für Hubschrauber, Wegweisern, Schneezäunen oder dgl.
Hump-type crosswalk with buried signal lights and Hump type crosswalk construction method
Europäisches Patentamt | 2020
|Europäisches Patentamt | 2021
|