PREDICTION METHOD OF CONSTRUCTION TIMING, PREDICTION DEVICE AND CONCRETE CONSTRUCTION METHOD
To provide a method for predicting concrete construction timing, a prediction device, and a concrete construction method that can easily predict construction timing.SOLUTION: There provided steps of determining intercept information corresponding to measured initial temperature, estimating elapsed time from the determined intercept information and time of water pouring until a predetermined penetration resistance value is reached, measuring temperature of the concrete at time obtained by adding time obtained by subtracting predetermined subtraction time from the estimated elapsed time to the time of water pouring to the concrete, obtaining slope information corresponding to the measured temperature of the concrete, and determining an approximate equation representing the relationship between the penetration resistance and the elapsed time by using the obtained slope information and the intercept information to predict construction timing of the pushing operation.SELECTED DRAWING: Figure 5
【課題】施工タイミングを容易に予測することができるコンクリートの施工タイミングの予測方法、予測装置およびコンクリートの施工方法を提供する。【解決手段】測定した初期温度に対応する切片情報を求めるステップと、求めた切片情報と注水時刻から所定の貫入抵抗値に達するまでの経過時間を推定するステップと、推定した経過時間から所定の減算時間を減算して得られる時間を、コンクリートの注水時刻に加算して得られる時刻において、コンクリートの温度を測定するステップと、測定したコンクリートの温度に対応する傾き情報を求めるステップと、求めた傾き情報と切片情報を用いて、貫入抵抗値と経過時間の関係を表す近似式を決定し、押え作業の施工タイミングとして予測するステップとを有するようにする。【選択図】図5
PREDICTION METHOD OF CONSTRUCTION TIMING, PREDICTION DEVICE AND CONCRETE CONSTRUCTION METHOD
To provide a method for predicting concrete construction timing, a prediction device, and a concrete construction method that can easily predict construction timing.SOLUTION: There provided steps of determining intercept information corresponding to measured initial temperature, estimating elapsed time from the determined intercept information and time of water pouring until a predetermined penetration resistance value is reached, measuring temperature of the concrete at time obtained by adding time obtained by subtracting predetermined subtraction time from the estimated elapsed time to the time of water pouring to the concrete, obtaining slope information corresponding to the measured temperature of the concrete, and determining an approximate equation representing the relationship between the penetration resistance and the elapsed time by using the obtained slope information and the intercept information to predict construction timing of the pushing operation.SELECTED DRAWING: Figure 5
【課題】施工タイミングを容易に予測することができるコンクリートの施工タイミングの予測方法、予測装置およびコンクリートの施工方法を提供する。【解決手段】測定した初期温度に対応する切片情報を求めるステップと、求めた切片情報と注水時刻から所定の貫入抵抗値に達するまでの経過時間を推定するステップと、推定した経過時間から所定の減算時間を減算して得られる時間を、コンクリートの注水時刻に加算して得られる時刻において、コンクリートの温度を測定するステップと、測定したコンクリートの温度に対応する傾き情報を求めるステップと、求めた傾き情報と切片情報を用いて、貫入抵抗値と経過時間の関係を表す近似式を決定し、押え作業の施工タイミングとして予測するステップとを有するようにする。【選択図】図5
PREDICTION METHOD OF CONSTRUCTION TIMING, PREDICTION DEVICE AND CONCRETE CONSTRUCTION METHOD
コンクリートの施工タイミングの予測方法、予測装置およびコンクリートの施工方法
TAKEMOTO YOSHIAKI (Autor:in) / SAITO RYOSUKE (Autor:in)
30.05.2022
Patent
Elektronische Ressource
Japanisch
Europäisches Patentamt | 2022
|Europäisches Patentamt | 2021
|Construction method of shield tunnel segment concrete shrinkage prediction model
Europäisches Patentamt | 2021
|Prediction of Concrete Strength Development During Construction
British Library Conference Proceedings | 1994
|CONCRETE SLAB CONSTRUCTION DEVICE AND CONCRETE SLAB CONSTRUCTION METHOD
Europäisches Patentamt | 2018
|