UNDERFLOOR REINFORCEMENT METHOD AND UNDERFLOOR REINFORCEMENT STRUCTURE
To provide an underfloor reinforcement method or the like increased in strength in a reinforced place.SOLUTION: The underfloor reinforcement method for reinforcing an underfloor by filling a cavity 3 between a ground 2 and a floor 1 comprises: a step of forming a through-hole 4 connected to the cavity 3 in the floor 1; a step of inserting a rod-like drill from the through-hole 4 into the cavity 3 side to dig in the ground 2, and forming a longitudinal hole extending down from the cavity 3 directly below the through-hole 4; a step of supplying a liquid ground reinforcement 5 from the through-hole 4 into the cavity 3 and the longitudinal hole; a step of inserting the drill from the through-hole 4 into the longitudinal hole and stirring the ground reinforcement 5 in the longitudinal hole to permeate the ground reinforcement 5 through soil around the longitudinal hole, and retaining the shape of the longitudinal hole through curing action of the ground reinforcement 5; a step of supplying a foaming resin from the through-hole 4 to fill the cavity 3 and the longitudinal hole; and a step of closing the through-hole 4 after the cavity 3 and the longitudinal hole have been filled with the foaming resin.SELECTED DRAWING: Figure 6
【課題】補強箇所の強度が向上した床下補強方法等の提供。【解決手段】本発明の床下補強方法は、地盤2と、床1との間の空洞3を埋めることで床下を補強する床下補強方法であって、床1に、空洞3と繋がる貫通孔4を形成する工程と、貫通孔4から空洞3側に棒状のドリルを挿入して地盤2を掘り下げ、貫通孔4の真下に、空洞3から下方に延びた縦穴を形成する工程と、貫通孔4から空洞3及び縦穴に液状の地盤強化剤5を供給する工程と、貫通孔4から縦穴にドリルを挿入して縦穴内の地盤強化剤5を攪拌することにより、地盤強化剤5を縦穴の周囲の土壌に浸透させて、地盤強化剤5による硬化作用により、縦穴の形状を保持させる工程と、その後、貫通孔4から空洞3及び縦穴を埋めるように、発泡性樹脂を供給する工程と、空洞3及び縦穴が、発泡性樹脂で埋められた後、貫通孔4を塞ぐ工程とを備える。【選択図】図6
UNDERFLOOR REINFORCEMENT METHOD AND UNDERFLOOR REINFORCEMENT STRUCTURE
To provide an underfloor reinforcement method or the like increased in strength in a reinforced place.SOLUTION: The underfloor reinforcement method for reinforcing an underfloor by filling a cavity 3 between a ground 2 and a floor 1 comprises: a step of forming a through-hole 4 connected to the cavity 3 in the floor 1; a step of inserting a rod-like drill from the through-hole 4 into the cavity 3 side to dig in the ground 2, and forming a longitudinal hole extending down from the cavity 3 directly below the through-hole 4; a step of supplying a liquid ground reinforcement 5 from the through-hole 4 into the cavity 3 and the longitudinal hole; a step of inserting the drill from the through-hole 4 into the longitudinal hole and stirring the ground reinforcement 5 in the longitudinal hole to permeate the ground reinforcement 5 through soil around the longitudinal hole, and retaining the shape of the longitudinal hole through curing action of the ground reinforcement 5; a step of supplying a foaming resin from the through-hole 4 to fill the cavity 3 and the longitudinal hole; and a step of closing the through-hole 4 after the cavity 3 and the longitudinal hole have been filled with the foaming resin.SELECTED DRAWING: Figure 6
【課題】補強箇所の強度が向上した床下補強方法等の提供。【解決手段】本発明の床下補強方法は、地盤2と、床1との間の空洞3を埋めることで床下を補強する床下補強方法であって、床1に、空洞3と繋がる貫通孔4を形成する工程と、貫通孔4から空洞3側に棒状のドリルを挿入して地盤2を掘り下げ、貫通孔4の真下に、空洞3から下方に延びた縦穴を形成する工程と、貫通孔4から空洞3及び縦穴に液状の地盤強化剤5を供給する工程と、貫通孔4から縦穴にドリルを挿入して縦穴内の地盤強化剤5を攪拌することにより、地盤強化剤5を縦穴の周囲の土壌に浸透させて、地盤強化剤5による硬化作用により、縦穴の形状を保持させる工程と、その後、貫通孔4から空洞3及び縦穴を埋めるように、発泡性樹脂を供給する工程と、空洞3及び縦穴が、発泡性樹脂で埋められた後、貫通孔4を塞ぐ工程とを備える。【選択図】図6
UNDERFLOOR REINFORCEMENT METHOD AND UNDERFLOOR REINFORCEMENT STRUCTURE
床下補強方法、及び床下補強構造
NISHIMURA TOSHIO (Autor:in)
13.12.2023
Patent
Elektronische Ressource
Japanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
UNDERFLOOR REINFORCEMENT STRUCTURE, AND REINFORCEMENT METHOD OF UNDERFLOOR REINFORCEMENT STRUCTURE
Europäisches Patentamt | 2022
|UNDERFLOOR WIRING STRUCTURE AND UNDERFLOOR WIRING METHOD
Europäisches Patentamt | 2024
|UNDERFLOOR WIRING STRUCTURE AND METHOD FOR UNDERFLOOR WIRING
Europäisches Patentamt | 2022
|