Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
CONCRETE PLACING PIPING
To provide concrete placing piping which can suppress separation of a concrete material even if a giant structure is constructed.SOLUTION: In concrete placing piping 10, a pipe body 12 has a first lift part 12A, and a second lift part 12B which is a region with a second height H2 from a first height H1. There are performed first placing of discharging concrete C from a hole 15 formed in the first lift part 12A, and placing the concrete C up to the first height H1, and second placing of discharging concrete from a hole 15 formed in the second lift part 12B over days from the first placing, and placing the concrete up to the second height H2. A distance X1 between a hole 15 positioned at the bottom of the second lift part 12B in the plurality of holes 15 and a first boundary part Z1 is longer than a distance between a hole 15 positioned at the top of the first lift part 12A and the first boundary part Z1.SELECTED DRAWING: Figure 9
【課題】巨大な構造物を構築する場合であってもコンクリートの材料分離を抑制できるコンクリート打設配管を提供する。【解決手段】一実施形態に係るコンクリート打設配管10において、管本体12は、第1リフト部12Aと、第1高さH1から第2高さH2の領域である第2リフト部12Bとを有する。第1リフト部12Aに形成された孔15からコンクリートCを吐出して第1高さH1までコンクリートCを打設する第1打設、及び、第1打設から日を跨いだ後に第2リフト部12Bに形成された孔15からコンクリートを吐出して第2高さH2までコンクリートを打設する第2打設が行われる。複数の孔15のうち第2リフト部12Bの最も下に位置する孔15から第1境界部Z1までの距離X1は、第1リフト部12Aの最も上に位置する孔15から第1境界部Z1までの距離より長い。【選択図】図9
CONCRETE PLACING PIPING
To provide concrete placing piping which can suppress separation of a concrete material even if a giant structure is constructed.SOLUTION: In concrete placing piping 10, a pipe body 12 has a first lift part 12A, and a second lift part 12B which is a region with a second height H2 from a first height H1. There are performed first placing of discharging concrete C from a hole 15 formed in the first lift part 12A, and placing the concrete C up to the first height H1, and second placing of discharging concrete from a hole 15 formed in the second lift part 12B over days from the first placing, and placing the concrete up to the second height H2. A distance X1 between a hole 15 positioned at the bottom of the second lift part 12B in the plurality of holes 15 and a first boundary part Z1 is longer than a distance between a hole 15 positioned at the top of the first lift part 12A and the first boundary part Z1.SELECTED DRAWING: Figure 9
【課題】巨大な構造物を構築する場合であってもコンクリートの材料分離を抑制できるコンクリート打設配管を提供する。【解決手段】一実施形態に係るコンクリート打設配管10において、管本体12は、第1リフト部12Aと、第1高さH1から第2高さH2の領域である第2リフト部12Bとを有する。第1リフト部12Aに形成された孔15からコンクリートCを吐出して第1高さH1までコンクリートCを打設する第1打設、及び、第1打設から日を跨いだ後に第2リフト部12Bに形成された孔15からコンクリートを吐出して第2高さH2までコンクリートを打設する第2打設が行われる。複数の孔15のうち第2リフト部12Bの最も下に位置する孔15から第1境界部Z1までの距離X1は、第1リフト部12Aの最も上に位置する孔15から第1境界部Z1までの距離より長い。【選択図】図9
CONCRETE PLACING PIPING
コンクリート打設配管
MATSUMOTO SHUJI (Autor:in) / UBUKAWA HIROYUKI (Autor:in) / OZAWA EIJI (Autor:in) / YANAI SHUJI (Autor:in) / ASHIZAWA RYOICHI (Autor:in) / WATANABE KENZO (Autor:in) / SAKATA NOBORU (Autor:in)
12.09.2024
Patent
Elektronische Ressource
Japanisch
CONCRETE PLACING METHOD AND PIPING UNIT FOR PLACING CONCRETE
Europäisches Patentamt | 2023
|CONCRETE PLACING METHOD AND CONCRETE PLACING STRUCTURE
Europäisches Patentamt | 2017
|CONCRETE PLACING STRUCTURE, AND CONCRETE PLACING METHOD
Europäisches Patentamt | 2024
|