THE SLOPE REINFORCEMENT METHOD USING NATURAL STONE
The present invention relates to a slope reinforcing method using natural stone providing stability by making the center of gravity of the upper part of the natural stone toward a slope by a form of an inverted triangle, preventing separation by connecting the lower part of the natural stone to a drain block of a gabion shape embedded into a backfilling material, and preventing a soil loss due to rainwater by improving a drain capacity of the backfilling material using the drain block and preventing layer separation. To achieve the same, in the slope reinforcing method using natural stone capable of reinforcing the slope by gradually forming filling layers by stacking natural stone up away from the slope and filling soil between the slope and natural stone and connecting the slope and natural stone using a wire mesh per each filling layer, the center of gravity of the nature stone is headed toward the slope by being formed into a form of an inverted triangle. The wire mesh having a slope inclined downward from the upper side of the natural stone to the lower side is place on the filling layer. The front and rear ends of the wire mesh form a lap-joint unit by being partly wound on a reinforcing frame. In the lower part of the natural stone, the drain block of the gabion shape wherein small stone is filled is horizontally placed on the filling layer. In the upper part of the natural stone, an anchor connected to the reinforcing frame formed on the front end of the wire mesh is formed. In the lower part of the natural stone, an anchor connected to the front end of the drain block is formed. A column joined to the reinforcing frame formed on the rear end of the wire mesh is embedded into the slope.
본 발명은 자연석을 역삼각형 형태로 이용하여 상부쪽 무게중심이 경사면으로 향해 안정감을 주고 또한 자연석의 하부쪽은 뒷채움재에 매립되는 돌망태 형태의 배수블록과 연결하여 들뜨지 않도록 하였으며, 상기 배수블록에 의해 뒷채움재의 배수성이 향상되고 층 분리가 억제되어 빗물에 의한 토사유실이 발생되지 않는 자연석을 이용한 경사면 보강공법에 관한 것이다. 이를 위하여 본 발명은 경사면과 떨어져서 자연석을 다단으로 쌓고 이들 경사면과 자연석 사이에 흙을 채워 성토층을 단계적으로 만들며, 성토층마다 경사면과 자연석을 와이어매쉬로 연결하여 경사면이 보강되도록 한 자연석을 이용한 경사면 보강공법에 있어서, 상기 자연석은 역삼각형 형태로 구성되어 무게중심이 상기 경사면 쪽으로 향하게 제작되고; 상기 와이어매쉬는 상기 자연석의 상부쪽에서 하부쪽으로 하향 경사진 기울기를 가지며 상기 성토층에 깔리고, 상기 와이어매쉬의 선단 및 후단은 보강프레임에 일부가 감긴 겹이음부로 구성되며; 상기 자연석의 하부쪽은 작은 돌이 채워진 돌망태 형태의 배수블록이 성토층에 수평으로 깔리고; 상기 자연석의 상부쪽은 상기 와이어매쉬의 선단에 구비된 보강프레임과 연결되는 앵커가 구비되고, 하부쪽은 상기 배수블록의 선단과 연결되는 앵커가 구비되며; 상기 경사면에는 상기 와이어매쉬의 후단에 구비된 보강프레임과 결합되는 기둥이 박히도록 한 특징이 있다.
THE SLOPE REINFORCEMENT METHOD USING NATURAL STONE
The present invention relates to a slope reinforcing method using natural stone providing stability by making the center of gravity of the upper part of the natural stone toward a slope by a form of an inverted triangle, preventing separation by connecting the lower part of the natural stone to a drain block of a gabion shape embedded into a backfilling material, and preventing a soil loss due to rainwater by improving a drain capacity of the backfilling material using the drain block and preventing layer separation. To achieve the same, in the slope reinforcing method using natural stone capable of reinforcing the slope by gradually forming filling layers by stacking natural stone up away from the slope and filling soil between the slope and natural stone and connecting the slope and natural stone using a wire mesh per each filling layer, the center of gravity of the nature stone is headed toward the slope by being formed into a form of an inverted triangle. The wire mesh having a slope inclined downward from the upper side of the natural stone to the lower side is place on the filling layer. The front and rear ends of the wire mesh form a lap-joint unit by being partly wound on a reinforcing frame. In the lower part of the natural stone, the drain block of the gabion shape wherein small stone is filled is horizontally placed on the filling layer. In the upper part of the natural stone, an anchor connected to the reinforcing frame formed on the front end of the wire mesh is formed. In the lower part of the natural stone, an anchor connected to the front end of the drain block is formed. A column joined to the reinforcing frame formed on the rear end of the wire mesh is embedded into the slope.
본 발명은 자연석을 역삼각형 형태로 이용하여 상부쪽 무게중심이 경사면으로 향해 안정감을 주고 또한 자연석의 하부쪽은 뒷채움재에 매립되는 돌망태 형태의 배수블록과 연결하여 들뜨지 않도록 하였으며, 상기 배수블록에 의해 뒷채움재의 배수성이 향상되고 층 분리가 억제되어 빗물에 의한 토사유실이 발생되지 않는 자연석을 이용한 경사면 보강공법에 관한 것이다. 이를 위하여 본 발명은 경사면과 떨어져서 자연석을 다단으로 쌓고 이들 경사면과 자연석 사이에 흙을 채워 성토층을 단계적으로 만들며, 성토층마다 경사면과 자연석을 와이어매쉬로 연결하여 경사면이 보강되도록 한 자연석을 이용한 경사면 보강공법에 있어서, 상기 자연석은 역삼각형 형태로 구성되어 무게중심이 상기 경사면 쪽으로 향하게 제작되고; 상기 와이어매쉬는 상기 자연석의 상부쪽에서 하부쪽으로 하향 경사진 기울기를 가지며 상기 성토층에 깔리고, 상기 와이어매쉬의 선단 및 후단은 보강프레임에 일부가 감긴 겹이음부로 구성되며; 상기 자연석의 하부쪽은 작은 돌이 채워진 돌망태 형태의 배수블록이 성토층에 수평으로 깔리고; 상기 자연석의 상부쪽은 상기 와이어매쉬의 선단에 구비된 보강프레임과 연결되는 앵커가 구비되고, 하부쪽은 상기 배수블록의 선단과 연결되는 앵커가 구비되며; 상기 경사면에는 상기 와이어매쉬의 후단에 구비된 보강프레임과 결합되는 기둥이 박히도록 한 특징이 있다.
THE SLOPE REINFORCEMENT METHOD USING NATURAL STONE
자연석을 이용한 경사면 보강공법
CHOI DOOK HO (Autor:in)
15.06.2015
Patent
Elektronische Ressource
Koreanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Europäisches Patentamt | 2019
|Slope reinforcement construction method using vegetation soil and slope reinforcement construction
Europäisches Patentamt | 2021
|Slope reinforcement method and slope reinforcement structure using artificial rock blocks
Europäisches Patentamt | 2022
|