CONSTRUCTION METHOD FOR PERPENDICULAR HALL
The present invention relates to a vertical shaft construction method where a plurality of vertical shaft modules (100) are stacked to be coupled. The vertical shaft construction method comprises: a lower guide member preparation step of preparing a lower side coupling unit (510), a lower side extension unit (520), and a lower side guide member (500); an upper side guide member preparation step of preparing an upper side coupling unit (610), an upper side extension unit (620), and an upper side guide member (600) having an insertion hole (630); a first vertical shaft module installation step of installing a first vertical shaft module (100A); a guide member coupling step of enabling the lower side guide member (500) to be coupled to an upper end extension unit (113A); and a module coupling step of enabling a protruding unit (530) to be inserted into the insertion hole (630) of the upper side guide member (600). Therefore, the vertical shaft construction method can significantly reduce a construction period.
본 발명은 상하단에 트임부가 형성되고 심부에 상하방향 관통공이 형성된 통형 벽체(110)와, 상기 통형 벽체(110)의 하단에서 내측으로 돌출형성된 하단 연장부(112)와, 상기 통형 벽체(110)의 상단에서 내측으로 돌출형성된 상단 연장부(113)를 포함하는 복수의 수직갱 모듈(100)을 적층하여 결합하는 수직갱 시공방법으로서, 상기 상단 연장부(113)에 결합하도록 형성된 하측 결합부(510)와, 상기 하측 결합부(510)에서 상기 통형 벽체(110)의 내측방향으로 연장형성된 하측 연장부(520)와, 상기 하측 연장부(520)에서 상측으로 연장형성된 돌출부(530)를 포함하는 하측 유도부재(500)를 준비하는 하측 유도부재 준비단계; 상기 하단 연장부(112)에 결합하도록 형성된 상측 결합부(610)와, 상기 상측 결합부(610)에서 상기 통형 벽체(110)의 내측방향으로 연장형성된 상측 연장부(620)와, 상기 돌출부(530)가 삽입되도록 상기 상측 연장부(620)에 형성된 삽입공(630)을 포함하는 상측 유도부재(600)를 준비하는 상측 유도부재 준비단계; 상기 복수의 수직갱 모듈(100) 중 제1 수직갱 모듈(100A)을 설치하는 제1 수직갱 모듈 설치단계; 상기 제1 수직갱 모듈(100A)의 상단 연장부(113A)에 상기 하측 유도부재(500)를 결합하고, 상기 복수의 수직갱 모듈(100) 중 제2 수직갱 모듈(100B)의 하단 연장부(112B)에 상기 상측 유도부재(600)를 결합하는 유도부재 결합단계; 인양장치에 의해 상기 제2 수직갱 모듈(100B)을 인양하여 상기 제1 수직갱 모듈(100A)의 상부에 위치시키되, 상기 제2 수직갱 모듈(100B)에 결합한 상기 상측 유도부재(600)의 삽입공(630)에 대하여, 상기 제1 수직갱 모듈(100A)에 결합한 상기 하측 유도부재(500)의 돌출부(530)가 삽입되도록 하는 모듈결합단계;를 포함하는 것을 특징으로 하는 수직갱 시공방법을 제시함으로써, 안전사고의 우려가 적으면서도 공기를 크게 단축할 수 있도록 한다.
CONSTRUCTION METHOD FOR PERPENDICULAR HALL
The present invention relates to a vertical shaft construction method where a plurality of vertical shaft modules (100) are stacked to be coupled. The vertical shaft construction method comprises: a lower guide member preparation step of preparing a lower side coupling unit (510), a lower side extension unit (520), and a lower side guide member (500); an upper side guide member preparation step of preparing an upper side coupling unit (610), an upper side extension unit (620), and an upper side guide member (600) having an insertion hole (630); a first vertical shaft module installation step of installing a first vertical shaft module (100A); a guide member coupling step of enabling the lower side guide member (500) to be coupled to an upper end extension unit (113A); and a module coupling step of enabling a protruding unit (530) to be inserted into the insertion hole (630) of the upper side guide member (600). Therefore, the vertical shaft construction method can significantly reduce a construction period.
본 발명은 상하단에 트임부가 형성되고 심부에 상하방향 관통공이 형성된 통형 벽체(110)와, 상기 통형 벽체(110)의 하단에서 내측으로 돌출형성된 하단 연장부(112)와, 상기 통형 벽체(110)의 상단에서 내측으로 돌출형성된 상단 연장부(113)를 포함하는 복수의 수직갱 모듈(100)을 적층하여 결합하는 수직갱 시공방법으로서, 상기 상단 연장부(113)에 결합하도록 형성된 하측 결합부(510)와, 상기 하측 결합부(510)에서 상기 통형 벽체(110)의 내측방향으로 연장형성된 하측 연장부(520)와, 상기 하측 연장부(520)에서 상측으로 연장형성된 돌출부(530)를 포함하는 하측 유도부재(500)를 준비하는 하측 유도부재 준비단계; 상기 하단 연장부(112)에 결합하도록 형성된 상측 결합부(610)와, 상기 상측 결합부(610)에서 상기 통형 벽체(110)의 내측방향으로 연장형성된 상측 연장부(620)와, 상기 돌출부(530)가 삽입되도록 상기 상측 연장부(620)에 형성된 삽입공(630)을 포함하는 상측 유도부재(600)를 준비하는 상측 유도부재 준비단계; 상기 복수의 수직갱 모듈(100) 중 제1 수직갱 모듈(100A)을 설치하는 제1 수직갱 모듈 설치단계; 상기 제1 수직갱 모듈(100A)의 상단 연장부(113A)에 상기 하측 유도부재(500)를 결합하고, 상기 복수의 수직갱 모듈(100) 중 제2 수직갱 모듈(100B)의 하단 연장부(112B)에 상기 상측 유도부재(600)를 결합하는 유도부재 결합단계; 인양장치에 의해 상기 제2 수직갱 모듈(100B)을 인양하여 상기 제1 수직갱 모듈(100A)의 상부에 위치시키되, 상기 제2 수직갱 모듈(100B)에 결합한 상기 상측 유도부재(600)의 삽입공(630)에 대하여, 상기 제1 수직갱 모듈(100A)에 결합한 상기 하측 유도부재(500)의 돌출부(530)가 삽입되도록 하는 모듈결합단계;를 포함하는 것을 특징으로 하는 수직갱 시공방법을 제시함으로써, 안전사고의 우려가 적으면서도 공기를 크게 단축할 수 있도록 한다.
CONSTRUCTION METHOD FOR PERPENDICULAR HALL
수직갱 시공방법
RHEE JONG WHA (Autor:in) / SHIN JUN HYUM (Autor:in) / HWANG YOUNG CHUL (Autor:in)
13.06.2016
Patent
Elektronische Ressource
Koreanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
PERPENDICULAR HALL MODULE AND CONSTRUCTION METHOD FOR PERPENDICULAR HALL USING THE SAME
Europäisches Patentamt | 2016
|PERPENDICULAR HALL MODULE AND CONSTRUCTION METHOD FOR PERPENDICULAR HALL USING THE SAME
Europäisches Patentamt | 2015
|JOINT STRUCTURE FOR PERPENDICULAR HALL AND HORIZONTAL HALL