Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Cable Bridge and Constructing Method thereof
The present invention provides a cable bridge construction method and a cable bridge built by using the same. In the cable bridge construction method, multiple floor cables (1) as well as multiple horizontal beams (2) are installed. A pair of main cables (4) are installed above the horizontal beams (2) in a horizontal direction to have a gap greater than the length of the horizontal beams (2) in the horizontal direction. A tilted upper hanger (41) hangs the horizontal beams (2) on the main cables (4). A floor plate is installed (3). A pair of wind cables (5) are also installed. The wind cables (5) are bound with the horizontal beams (2). Accordingly, a cable bridge (100), which has a support force suppressing the fluctuation and twisting, can be built by using the main cables (4), upper hanger (41), and wind cables (5).
본 발명에서는 복수개의 바닥 케이블(1)을 설치하고, 복수개의 가로보(2)를 설치하고, 한 쌍의 메인 케이블(4)을 가로보(2)의 위쪽에서 횡방향으로 가로보(2)의 횡방향 길이보다 더 큰 간격을 두고 설치하고, 경사진 상부 행어(41)에 의해 가로보(2)가 메인 케이블(4)에 매달리게 만들고, 바닥판(3)을 설치하며, 한 쌍의 윈드 케이블(5)을 설치하고, 윈드 케이블(5)을 가로보(2)와 결속함으로써, 메인 케이블(4)과 상부 행어(41), 그리고 윈드 케이블(5)에 의해 출렁거림 및 비틀림을 억제하는 지지력이 발휘되는 구성을 가지는 케이블 교량(100)을 시공하게 되는 것을 특징으로 하는 케이블 교량의 시공방법과, 이러한 시공방법에 의해 구축되는 케이블 교량이 제공된다.
Cable Bridge and Constructing Method thereof
The present invention provides a cable bridge construction method and a cable bridge built by using the same. In the cable bridge construction method, multiple floor cables (1) as well as multiple horizontal beams (2) are installed. A pair of main cables (4) are installed above the horizontal beams (2) in a horizontal direction to have a gap greater than the length of the horizontal beams (2) in the horizontal direction. A tilted upper hanger (41) hangs the horizontal beams (2) on the main cables (4). A floor plate is installed (3). A pair of wind cables (5) are also installed. The wind cables (5) are bound with the horizontal beams (2). Accordingly, a cable bridge (100), which has a support force suppressing the fluctuation and twisting, can be built by using the main cables (4), upper hanger (41), and wind cables (5).
본 발명에서는 복수개의 바닥 케이블(1)을 설치하고, 복수개의 가로보(2)를 설치하고, 한 쌍의 메인 케이블(4)을 가로보(2)의 위쪽에서 횡방향으로 가로보(2)의 횡방향 길이보다 더 큰 간격을 두고 설치하고, 경사진 상부 행어(41)에 의해 가로보(2)가 메인 케이블(4)에 매달리게 만들고, 바닥판(3)을 설치하며, 한 쌍의 윈드 케이블(5)을 설치하고, 윈드 케이블(5)을 가로보(2)와 결속함으로써, 메인 케이블(4)과 상부 행어(41), 그리고 윈드 케이블(5)에 의해 출렁거림 및 비틀림을 억제하는 지지력이 발휘되는 구성을 가지는 케이블 교량(100)을 시공하게 되는 것을 특징으로 하는 케이블 교량의 시공방법과, 이러한 시공방법에 의해 구축되는 케이블 교량이 제공된다.
Cable Bridge and Constructing Method thereof
출렁거림 및 비틀림 억제 구조를 가지는 케이블 교량의 시공방법 및 이에 의해 시공된 케이블 교량
NA HYUN GEUN (Autor:in) / KIM SE JONG (Autor:in)
23.11.2016
Patent
Elektronische Ressource
Koreanisch
IPC:
E01D
BRIDGES
,
Brücken
Cable-Stayed Bridge having Precast Core and Constructing Method thereof
Europäisches Patentamt | 2017
|Cable-Stayed Bridge having Precast Core and Constructing Method thereof
Europäisches Patentamt | 2018
CONSTRUCTING METHOD OF WIND CABLE IN SUSPENDING BRIDGE
Europäisches Patentamt | 2016
|Method for constructing bridge cable fiber sealing protection system
Europäisches Patentamt | 2021
|