Bridge construction using integral abutment
The present invention relates to an integrated type construction method of an abutment bridge, securing durability to increase durability of a bridge and significantly reducing maintenance costs. The integrated type construction method of an abutment bridge comprises: a bank step of performing a work of a bank unit of both side abutments of the bridge; a piling step of piling an H pile; an abutment first stage construction step of forming a pile capping unit covering an upper end part of the H pile; a beam placing step of enabling a beam to be placed in an upper portion of the pile capping unit; an upper slab and abutment second stage application step of applying concrete to the upper portion of the beam and the pile capping unit; a backfilling step of performing the bank work on a rear surface of the abutment; and a connection slab construction step of applying the concrete to the upper portion of a backfilling unit and the abutment.
본 발명은 내구성을 확보하여 교량의 수명을 늘리면서도 유지보수 비용을 현저히 줄일 수 있도록 한 일체식 교대 교량의 시공방법에 관한 것으로, 교량 양측 교대 제방부의 성토 작업을 수행하는 성토 단계, H 파일을 항타하는 항타 단계, 상기 H 파일 상단부를 덮어씌우는 파일 캐핑부를 형성하는 교대 1 단 시공 단계, 빔을 상기 파일 캐핑부에 상부에 거치하는 빔 거치 단계, 상기 빔과 파일 캐핑부 상부에 콘크리트를 타설하는 상부 슬래브 및 교대 2단 타설 단계, 교대 배면에 성토 작업을 수행하는 뒷채움 단계 및 뒷채움부 및 교대의 상부에 콘크리트를 타설하는 접속 슬래브 시공 단계를 포함하여 구성되는 것을 특징으로 한다.
Bridge construction using integral abutment
The present invention relates to an integrated type construction method of an abutment bridge, securing durability to increase durability of a bridge and significantly reducing maintenance costs. The integrated type construction method of an abutment bridge comprises: a bank step of performing a work of a bank unit of both side abutments of the bridge; a piling step of piling an H pile; an abutment first stage construction step of forming a pile capping unit covering an upper end part of the H pile; a beam placing step of enabling a beam to be placed in an upper portion of the pile capping unit; an upper slab and abutment second stage application step of applying concrete to the upper portion of the beam and the pile capping unit; a backfilling step of performing the bank work on a rear surface of the abutment; and a connection slab construction step of applying the concrete to the upper portion of a backfilling unit and the abutment.
본 발명은 내구성을 확보하여 교량의 수명을 늘리면서도 유지보수 비용을 현저히 줄일 수 있도록 한 일체식 교대 교량의 시공방법에 관한 것으로, 교량 양측 교대 제방부의 성토 작업을 수행하는 성토 단계, H 파일을 항타하는 항타 단계, 상기 H 파일 상단부를 덮어씌우는 파일 캐핑부를 형성하는 교대 1 단 시공 단계, 빔을 상기 파일 캐핑부에 상부에 거치하는 빔 거치 단계, 상기 빔과 파일 캐핑부 상부에 콘크리트를 타설하는 상부 슬래브 및 교대 2단 타설 단계, 교대 배면에 성토 작업을 수행하는 뒷채움 단계 및 뒷채움부 및 교대의 상부에 콘크리트를 타설하는 접속 슬래브 시공 단계를 포함하여 구성되는 것을 특징으로 한다.
Bridge construction using integral abutment
일체식 교대 교량의 시공방법
KIM IK JUNG (Autor:in)
31.01.2017
Patent
Elektronische Ressource
Koreanisch
Integral Abutment Bridge Design and Construction
NTIS | 1987
|Europäisches Patentamt | 2021
|Europäisches Patentamt | 2015
|Abutment reaming hole construction for optimizing deformation capability of integral abutment bridge
Europäisches Patentamt | 2015
|INTEGRAL ABUTMENT BRIDGE CONSTRUCTION METHOD OF OLD JOINT BUTMENT BRIDGE