Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Bridge bearing replacement method for preventing drop of upper structure
The present invention is to provide a bridge support replacement method for preventing a fall of an upper structure, which minimizes damage of a structure when replacing a support of an existing bridge, and normally absorbs the movement of an upper structure due to temperature changes and limits the displacement of the upper structure when an earthquake occurs, by integrating a new support into a lower structure (bridge stand, bridge pier) through upper and lower reinforcement plates and high-strength anchor bolts. According to a preferred embodiment of the present invention, the bridge support replacement method is performed through the following steps of: (a) installing a hydraulic jack between a bridge lower structure and a girder to raise an upper structure, and then removing an existing bridge support; (b) installing high-strength anchor bolts in anchor holes after perforating a predetermined number of anchor holes at a predetermined depth by using a side space of the girder (22) on the periphery where a new support is installed on the upper surface of the bridge lower structure; (c) constructing a support base with a predetermined thickness including a region where the high-strength anchor bolts are installed by using high-strength mortar; (d) inserting a lower reinforcement plate into the high-strength anchor bolt, supporting the lower reinforcement plate on the upper surface of the support base, and bonding the new support to the lower reinforcement plate by welding; (e) inserting an upper reinforcement plate into the high-strength anchor bolt, welding the upper reinforcement plate to the upper surface of the new support, and operating the hydraulic jack to lower the upper structure (20); and (f) inserting a side fixing member into the high-strength anchor bolt, fixating the side fixing member to the upper structure by using a fixing anchor bolt, and fastening a nut to the high-strength anchor bolt to fixate the side fixing member to the high-strength anchor bolt.
본 발명은 기존 교량의 받침 교체시 구조물의 손상을 최소화하고 신설받침을 상,하부 보강판 및 고강도 앵커볼트를 통해 하부구조물(교대, 교각)에 일체화시켜 평상시에는 온도변화에 따른 상부구조의 거동을 흡수하고 지진발생시에는 상부구조물의 변위를 제한함과 동시에 상부구조물의 추락방지를 겸하는 교량받침 교체 방법을 제공한다. 본 발명의 적절한 실시 형태에 따르면, (a) 교량 하부구조물과 거더의 사이에 유압잭을 설치하여 상부구조물을 인상시킨 후 기존 교량받침을 철거해내는 단계와; (b) 상기 교량 하부구조물의 상면에 신설받침이 설치되는 주변으로 거더(22)의 측면 공간을 이용하여 설정된 개수의 앵커홀을 일정 깊이만큼 천공한 후, 고강도 앵커볼트를 앵커홀에 설치하는 단계와; (c) 고강도 몰탈을 사용하여 상기 고강도 앵커볼트가 설치된 영역을 포함하여 일정 두께로 받침베이스를 시공하는 단계와; (d) 상기 고강도 앵커볼트에 하부보강판을 삽입시켜 상기 받침베이스의 상면에 지지시켜 놓고, 신설받침을 하부보강판에 용접으로 접합시켜 놓는 단계와; (e) 상부보강판을 상기 고강도 앵커볼트에 삽입시킨 후 상기 신설받침의 상면에 용접으로 접합시키고 상기 유압잭을 조작하여 상부구조물(20)을 하강시켜 놓는 단계와; (f) 측면고정부재를 상기 고강도 앵커볼트에 삽입시킨 후, 고정용 앵커볼트 측면고정부재를 상부구조물에 고정시키고, 상기 고강도 앵커볼트에 너트를 체결하여 측면고정부재를 상기 고강도 앵커볼트에 고정시켜 놓는 단계;를 포함하여 시공되는 것을 특징으로 한다.
Bridge bearing replacement method for preventing drop of upper structure
The present invention is to provide a bridge support replacement method for preventing a fall of an upper structure, which minimizes damage of a structure when replacing a support of an existing bridge, and normally absorbs the movement of an upper structure due to temperature changes and limits the displacement of the upper structure when an earthquake occurs, by integrating a new support into a lower structure (bridge stand, bridge pier) through upper and lower reinforcement plates and high-strength anchor bolts. According to a preferred embodiment of the present invention, the bridge support replacement method is performed through the following steps of: (a) installing a hydraulic jack between a bridge lower structure and a girder to raise an upper structure, and then removing an existing bridge support; (b) installing high-strength anchor bolts in anchor holes after perforating a predetermined number of anchor holes at a predetermined depth by using a side space of the girder (22) on the periphery where a new support is installed on the upper surface of the bridge lower structure; (c) constructing a support base with a predetermined thickness including a region where the high-strength anchor bolts are installed by using high-strength mortar; (d) inserting a lower reinforcement plate into the high-strength anchor bolt, supporting the lower reinforcement plate on the upper surface of the support base, and bonding the new support to the lower reinforcement plate by welding; (e) inserting an upper reinforcement plate into the high-strength anchor bolt, welding the upper reinforcement plate to the upper surface of the new support, and operating the hydraulic jack to lower the upper structure (20); and (f) inserting a side fixing member into the high-strength anchor bolt, fixating the side fixing member to the upper structure by using a fixing anchor bolt, and fastening a nut to the high-strength anchor bolt to fixate the side fixing member to the high-strength anchor bolt.
본 발명은 기존 교량의 받침 교체시 구조물의 손상을 최소화하고 신설받침을 상,하부 보강판 및 고강도 앵커볼트를 통해 하부구조물(교대, 교각)에 일체화시켜 평상시에는 온도변화에 따른 상부구조의 거동을 흡수하고 지진발생시에는 상부구조물의 변위를 제한함과 동시에 상부구조물의 추락방지를 겸하는 교량받침 교체 방법을 제공한다. 본 발명의 적절한 실시 형태에 따르면, (a) 교량 하부구조물과 거더의 사이에 유압잭을 설치하여 상부구조물을 인상시킨 후 기존 교량받침을 철거해내는 단계와; (b) 상기 교량 하부구조물의 상면에 신설받침이 설치되는 주변으로 거더(22)의 측면 공간을 이용하여 설정된 개수의 앵커홀을 일정 깊이만큼 천공한 후, 고강도 앵커볼트를 앵커홀에 설치하는 단계와; (c) 고강도 몰탈을 사용하여 상기 고강도 앵커볼트가 설치된 영역을 포함하여 일정 두께로 받침베이스를 시공하는 단계와; (d) 상기 고강도 앵커볼트에 하부보강판을 삽입시켜 상기 받침베이스의 상면에 지지시켜 놓고, 신설받침을 하부보강판에 용접으로 접합시켜 놓는 단계와; (e) 상부보강판을 상기 고강도 앵커볼트에 삽입시킨 후 상기 신설받침의 상면에 용접으로 접합시키고 상기 유압잭을 조작하여 상부구조물(20)을 하강시켜 놓는 단계와; (f) 측면고정부재를 상기 고강도 앵커볼트에 삽입시킨 후, 고정용 앵커볼트 측면고정부재를 상부구조물에 고정시키고, 상기 고강도 앵커볼트에 너트를 체결하여 측면고정부재를 상기 고강도 앵커볼트에 고정시켜 놓는 단계;를 포함하여 시공되는 것을 특징으로 한다.
Bridge bearing replacement method for preventing drop of upper structure
상부구조물의 추락방지를 겸하는 교량받침 교체 방법
SHIM KYU SOOK (Autor:in)
14.08.2017
Patent
Elektronische Ressource
Koreanisch
IPC:
E01D
BRIDGES
,
Brücken
BRIDGE BEARING REPLACEMENT METHOD AND BRIDGE BEARING STRUCTURE
Europäisches Patentamt | 2019
|CONSTRUCTION METHOD OF BRIDGE BEARING REPLACEMENT AND BRIDGE BEARING REPLACEMENT THEREOF
Europäisches Patentamt | 2015
|British Library Conference Proceedings | 1995
|Bridge bearing for replacement and replacement method.
Europäisches Patentamt | 2020
|