Construction method for underground vertical shaft structures
The present invention relates to a method to construct an underground vertical shaft structure, comprising: a first step of constructing a plurality of ground anchors on the ground at constant intervals along a wall of a vertical shaft structure to be constructed; a second step of installing a pressing leading edge shoe with a shape of a cross section of the vertical shaft structure on the ground; a third step of installing a unit structure, which is a part of the vertical shaft structure, on an upper side of the pressing leading edge shoe; a fourth step of installing a plurality of multistage grip rods at constant intervals along a wall of the unit structure and connecting the multistage grip rods to the ground anchors, respectively; a fifth step of installing a pressing beam, installing a ground pressing plate, or simultaneously installing the pressing beam and the ground pressing plate on an upper side of the unit structure, and installing a reciprocating hydraulic jack on an upper side of each multistage grip rod; and a sixth step of alternately repeating to excavate the ground inside the unit structure and to press and fixate the unit structure up to an excavation depth with the reciprocating hydraulic jack, so as to completely press and fixate the unit structure in the ground. Accordingly, due to an automatic pressing and fixating device using the ground anchor, the multistage grip rod, and the reciprocating hydraulic jack, provided are effects capable of quickly and safely pressing and fixating the unit structure to construct a vertical shaft without a temporary installation construction of an earth retaining wall; capable of preventing the underground structure from being rapidly sunken in a heterogeneous ground state; and capable of settling the ground anchor in a vertical shaft structure after completing a pressing and fixating construction, thus effectively resisting buoyance, withdrawal, eccentric load of foundation.
본 발명은 시공할 수직구 구조물의 벽체를 따라 일정 간격으로 복수의 지반앵커를 지반에 시공하는 1단계; 상기 수직구 구조물 단면모양의 압입선단슈를 상기 지반에 설치하는 2단계; 상기 압입선단슈 상측에 상기 수직구 구조물의 일부인 단위구조물을 설치하는 3단계; 복수의 다단그립롯드를 상기 단위구조물의 벽체를 따라 일정 간격으로 설치한 후 상기 복수의 지반앵커와 각각 연결하는 4단계; 상기 단위구조물의 상측에 가압빔을 설치하거나, 지압판을 설치하거나, 또는 가압빔과 지압판을 함께 설치하고, 상기 복수의 다단그립롯드 각각의 상측에 복동식유압잭을 설치하는 5단계; 상기 단위구조물의 내측 지반을 굴착하는 것과, 상기 복동식유압잭을 이용하여 상기 단위구조물을 상기 굴착 심도까지 압입하는 것을 번갈아 반복하여 상기 단위구조물을 지반에 완전 압입하는 6단계;를 포함하는 지하 수직구 구조물 시공방법에 관한 것으로서, 토류벽 등의 가설공사 없이 지반앵커와 다단그립롯드 및 복동식 유압잭을 이용한 자동화 압입장치로 안전하고 신속하게 수직구를 압입하여 시공할 수 있고, 불균질한 지반상태에서 지하구조물이 급격하게 침하되는 것을 예방할 수 있으며, 압입공사 완료 후에는 지반앵커를 수직구 구조물에 정착시킴으로써, 기초의 부력, 인발, 편심하중 등에 효과적으로 저항할 수 있는 효과를 제공할 수 있다.
Construction method for underground vertical shaft structures
The present invention relates to a method to construct an underground vertical shaft structure, comprising: a first step of constructing a plurality of ground anchors on the ground at constant intervals along a wall of a vertical shaft structure to be constructed; a second step of installing a pressing leading edge shoe with a shape of a cross section of the vertical shaft structure on the ground; a third step of installing a unit structure, which is a part of the vertical shaft structure, on an upper side of the pressing leading edge shoe; a fourth step of installing a plurality of multistage grip rods at constant intervals along a wall of the unit structure and connecting the multistage grip rods to the ground anchors, respectively; a fifth step of installing a pressing beam, installing a ground pressing plate, or simultaneously installing the pressing beam and the ground pressing plate on an upper side of the unit structure, and installing a reciprocating hydraulic jack on an upper side of each multistage grip rod; and a sixth step of alternately repeating to excavate the ground inside the unit structure and to press and fixate the unit structure up to an excavation depth with the reciprocating hydraulic jack, so as to completely press and fixate the unit structure in the ground. Accordingly, due to an automatic pressing and fixating device using the ground anchor, the multistage grip rod, and the reciprocating hydraulic jack, provided are effects capable of quickly and safely pressing and fixating the unit structure to construct a vertical shaft without a temporary installation construction of an earth retaining wall; capable of preventing the underground structure from being rapidly sunken in a heterogeneous ground state; and capable of settling the ground anchor in a vertical shaft structure after completing a pressing and fixating construction, thus effectively resisting buoyance, withdrawal, eccentric load of foundation.
본 발명은 시공할 수직구 구조물의 벽체를 따라 일정 간격으로 복수의 지반앵커를 지반에 시공하는 1단계; 상기 수직구 구조물 단면모양의 압입선단슈를 상기 지반에 설치하는 2단계; 상기 압입선단슈 상측에 상기 수직구 구조물의 일부인 단위구조물을 설치하는 3단계; 복수의 다단그립롯드를 상기 단위구조물의 벽체를 따라 일정 간격으로 설치한 후 상기 복수의 지반앵커와 각각 연결하는 4단계; 상기 단위구조물의 상측에 가압빔을 설치하거나, 지압판을 설치하거나, 또는 가압빔과 지압판을 함께 설치하고, 상기 복수의 다단그립롯드 각각의 상측에 복동식유압잭을 설치하는 5단계; 상기 단위구조물의 내측 지반을 굴착하는 것과, 상기 복동식유압잭을 이용하여 상기 단위구조물을 상기 굴착 심도까지 압입하는 것을 번갈아 반복하여 상기 단위구조물을 지반에 완전 압입하는 6단계;를 포함하는 지하 수직구 구조물 시공방법에 관한 것으로서, 토류벽 등의 가설공사 없이 지반앵커와 다단그립롯드 및 복동식 유압잭을 이용한 자동화 압입장치로 안전하고 신속하게 수직구를 압입하여 시공할 수 있고, 불균질한 지반상태에서 지하구조물이 급격하게 침하되는 것을 예방할 수 있으며, 압입공사 완료 후에는 지반앵커를 수직구 구조물에 정착시킴으로써, 기초의 부력, 인발, 편심하중 등에 효과적으로 저항할 수 있는 효과를 제공할 수 있다.
Construction method for underground vertical shaft structures
지하 수직구 구조물 시공방법
ROH KYUNG BEOM (Autor:in) / ROH U HYEON (Autor:in) / NO SIL GEUN (Autor:in) / NO YOK GEUN (Autor:in) / PARK CHI WOONG (Autor:in)
02.02.2018
Patent
Elektronische Ressource
Koreanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Europäisches Patentamt | 2016
|VERTICAL SHAFT CONSTRUCTION METHOD AND UNDERGROUND STORAGE TANK CONSTRUCTION METHOD
Europäisches Patentamt | 2016
|Pouring construction method for underground diaphragm wall of vertical shaft
Europäisches Patentamt | 2024
|VERTICAL SHAFT CONSTRUCTION DEVICE AND VERTICAL SHAFT CONSTRUCTION METHOD
Europäisches Patentamt | 2020
|Grooving construction method for ultra-deep vertical shaft underground diaphragm wall
Europäisches Patentamt | 2021
|