PRESTRESSED CONCRETE GIRDER BRIDGE AND METHOD CONSTRUCTING THE RESTRICT DEVICE USING THE SAME
The present invention relates to a construction method of a prestressed concrete girder bridge. More specifically, the present invention relates to an H-shaped steel assembly with a prestress introduced thereto and a construction method of a prestressed concrete girder bridge using the same, wherein the H-shaped steel assembly has a prestress introduced thereto by a restraint device, and the restraint device can be removed after introducing a prestress to the entire girder by installing an H-shaped steel assembly to which a prestress is introduced by the restraint device on the upper part of a concrete girder. According to the present invention, a construction method of a prestressed concrete girder bridge using an H-shaped steel assembly which is introduced by a restraint device comprises: a step of forming an H-shaped steel assembly by assembling a restraint device having a tensioning material to a flange of an H-shaped steel; a step of introducing a prestress into the H-shaped steel by tensioning the tensioning material of the restraint device; a step of installing the H-shaped steel assembly having the prestress introduced thereto on a reinforcing bar assembled to manufacture a girder; a step of depositing and curing girder concrete to embed the bottom flange of the H-shaped steel; a step of introducing a prestress to the girder by extending a PC steel wire inserted into the girder; a step of installing the girder having a prestress introduced thereto on an abutment and a pier; a step of installing a precast deck for depositing bottom plate concrete; a step of separating the restraint device from the H-shaped steel; and a step of depositing the bottom plate concrete.
본 발명은 프리스트레스트 콘크리트 거더교의 시공방법에 관한 것으로, 더욱 상세하게는 구속장치에 의해 프리스트레스가 도입된 H형강 조립체를 콘크리트 거더 상부에 설치하여 프리스트레스를 거더 전체에 도입한 후 구속장치를 제거할 수 있도록 한 구속장치에 의해 프리스트레스가 도입된 H형강 조립체 및 이를 이용한 프리스트레스트 콘크리트 거더교의 시공방법에 관한 것이다. 본 발명에 따른 구속장치에 의해 프리스트레스가 도입된 H형강 조립체를 이용한 프리스트레스트 콘크리트 거더교의 시공방법은, 긴장재가 구비된 구속장치를 H형강의 플랜지에 조립하여 H형강 조립체를 형성하는 단계; 구속장치의 긴장재를 인장하여 H형강에 프리스트레스를 도입하는 단계; 프리스트레스가 도입된 H형강 조립체를 거더 제작을 위해 조립된 철근 위에 설치하는 단계; H형강의 하부 플랜지가 매립되도록 거더 콘크리트를 타설하고 양생하는 단계; 거더에 삽입된 PC강선을 인장하여 거더에 프리스트레스를 도입하는 단계; 프리스트레스가 도입된 거더를 교대 및 교각 위에 설치하는 단계; 바닥판 콘크리트 타설을 위한 프리캐스트 데크를 설치하는 단계; H형강으로부터 구속장치를 분리하는 단계; 및 바닥판 콘크리트를 타설하는 단계; 를 포함한다.
PRESTRESSED CONCRETE GIRDER BRIDGE AND METHOD CONSTRUCTING THE RESTRICT DEVICE USING THE SAME
The present invention relates to a construction method of a prestressed concrete girder bridge. More specifically, the present invention relates to an H-shaped steel assembly with a prestress introduced thereto and a construction method of a prestressed concrete girder bridge using the same, wherein the H-shaped steel assembly has a prestress introduced thereto by a restraint device, and the restraint device can be removed after introducing a prestress to the entire girder by installing an H-shaped steel assembly to which a prestress is introduced by the restraint device on the upper part of a concrete girder. According to the present invention, a construction method of a prestressed concrete girder bridge using an H-shaped steel assembly which is introduced by a restraint device comprises: a step of forming an H-shaped steel assembly by assembling a restraint device having a tensioning material to a flange of an H-shaped steel; a step of introducing a prestress into the H-shaped steel by tensioning the tensioning material of the restraint device; a step of installing the H-shaped steel assembly having the prestress introduced thereto on a reinforcing bar assembled to manufacture a girder; a step of depositing and curing girder concrete to embed the bottom flange of the H-shaped steel; a step of introducing a prestress to the girder by extending a PC steel wire inserted into the girder; a step of installing the girder having a prestress introduced thereto on an abutment and a pier; a step of installing a precast deck for depositing bottom plate concrete; a step of separating the restraint device from the H-shaped steel; and a step of depositing the bottom plate concrete.
본 발명은 프리스트레스트 콘크리트 거더교의 시공방법에 관한 것으로, 더욱 상세하게는 구속장치에 의해 프리스트레스가 도입된 H형강 조립체를 콘크리트 거더 상부에 설치하여 프리스트레스를 거더 전체에 도입한 후 구속장치를 제거할 수 있도록 한 구속장치에 의해 프리스트레스가 도입된 H형강 조립체 및 이를 이용한 프리스트레스트 콘크리트 거더교의 시공방법에 관한 것이다. 본 발명에 따른 구속장치에 의해 프리스트레스가 도입된 H형강 조립체를 이용한 프리스트레스트 콘크리트 거더교의 시공방법은, 긴장재가 구비된 구속장치를 H형강의 플랜지에 조립하여 H형강 조립체를 형성하는 단계; 구속장치의 긴장재를 인장하여 H형강에 프리스트레스를 도입하는 단계; 프리스트레스가 도입된 H형강 조립체를 거더 제작을 위해 조립된 철근 위에 설치하는 단계; H형강의 하부 플랜지가 매립되도록 거더 콘크리트를 타설하고 양생하는 단계; 거더에 삽입된 PC강선을 인장하여 거더에 프리스트레스를 도입하는 단계; 프리스트레스가 도입된 거더를 교대 및 교각 위에 설치하는 단계; 바닥판 콘크리트 타설을 위한 프리캐스트 데크를 설치하는 단계; H형강으로부터 구속장치를 분리하는 단계; 및 바닥판 콘크리트를 타설하는 단계; 를 포함한다.
PRESTRESSED CONCRETE GIRDER BRIDGE AND METHOD CONSTRUCTING THE RESTRICT DEVICE USING THE SAME
추가 프리스트레스 도입이 가능한 프리스트레스트 콘크리트 거더교 시공방법 및 이에 사용되는 구속장치
KIM JOON YOUNG (Autor:in)
29.10.2018
Patent
Elektronische Ressource
Koreanisch
IPC:
E01D
BRIDGES
,
Brücken
PRESTRESSED CONCRETE GIRDER AND METHOD CONSTRUCTING THE GIRDER BRIDGE USING THE SAME
Europäisches Patentamt | 2015
|Europäisches Patentamt | 2017
|SEGMENTAL PRESTRESSED CONCRETE GIRDER AND METHOD FOR CONSTRUCTING SAME
Europäisches Patentamt | 2015
|Europäisches Patentamt | 2021
|SEGMENTAL PRESTRESSED CONCRETE GIRDER AND METHOD FOR CONSTRUCTING SAME
Europäisches Patentamt | 2016
|