Sub-beam materials for construction raised floor system supply of clean room way
The present invention relates to a method for supplying a sub beam material to a forklift (200) through a plurality of spaces (11) of a main beam (10) provided at a predetermined height in a lattice form for the construction of a double floor system of a clean room. Executed are a step of providing a position (100) where a turntable (110) is installed to be rotated by remote control operation; a first step of positioning the position (100) on the floor of one of the spaces (11) of the main beam (10); a second step of placing the sub beam materials (20) carried by a multi-stage forklift (200) on the turntable (110) of the position (100); a third step of lifting the position (100) where the sub beam materials (20) are placed to a predetermined height with the forklift (200) and then rotating the turntable (110) by a predetermined angle such that the longitudinal direction of the sub beam materials (20) is parallel to the longitudinal direction of the space (11) of the main beam (10); a fourth step of completely lifting the position (100) with the forklift (200) such that the rotated sub beam materials (20) are positioned to be higher than the main beam (10); and a fifth step of re-rotating the sub beam materials (20) higher than the main beam (10) to the turntable (110) and lowering the sub beam materials (20) such that the sub beam materials (20) are hung in a transverse direction on the main beam (10) and lowering the position (100) to the floor. When the first to fifth steps are repeated with the position (100) lowered after the execution of the steps, the sub beam materials (20) can be more safely supplied. In addition, material supply can be expedited, and thus labor cost reduction can be achieved along with workability improvement and construction cost reduction.
본 발명은 클린룸의 이중마루 시스템 시공을 위해 일정 높이에 격자형으로 설치된 메인빔(10)의 여러 공간(11)을 통해 지게차(200)로 서브빔 자재를 공급하는 방법에 관한 것으로서, 리모컨 조작으로 회전하도록 턴테이블(110)이 설치된 포지션(100)을 구비하는 단계와; 메인빔(10)의 여러 공간(11) 중 한 곳의 바닥에 포지션(100)을 위치시키는 제1단계; 다단식 지게차(200)로 실어온 다수의 서브빔 자재(20)를 포지션(100)의 턴테이블(110) 위에 올려 안착하는 제2단계; 서브빔 자재(20)가 놓인 포지션(100)을 지게차(200)로 일정 높이 들어올린 후 서브빔 자재(20)의 길이방향이 메인빔(10)의 공간(11) 길이 방향과 평행하도록 턴테이블(110)을 일정 각도 회전시키는 제3단계; 상기 회전된 서브빔 자재(20)가 메인빔(10) 보다 높게 위치되도록 포지션(100)을 지게차(200)로 완전히 올리는 제4단계: 메인빔(10) 보다 높이 위치된 서브빔 자재(20)를 턴테이블(110)로 다시 회전시킨 후 내려서 메인빔(10)에 횡방향으로 걸쳐지게 하고, 포지션(100)은 바닥을 향해 하강시키는 제5단계; 를 행한 후 하강된 포지션(100)으로 상기 제1단계 부터 제5단계를 반복하면 서브빔 자재(20)를 종래보다 안전하게 공급할 수 있으며, 자재 공급이 신속하므로 인건비 절감과 작업성 향상으로 시공비를 낮출 수 있는 것이다.
Sub-beam materials for construction raised floor system supply of clean room way
The present invention relates to a method for supplying a sub beam material to a forklift (200) through a plurality of spaces (11) of a main beam (10) provided at a predetermined height in a lattice form for the construction of a double floor system of a clean room. Executed are a step of providing a position (100) where a turntable (110) is installed to be rotated by remote control operation; a first step of positioning the position (100) on the floor of one of the spaces (11) of the main beam (10); a second step of placing the sub beam materials (20) carried by a multi-stage forklift (200) on the turntable (110) of the position (100); a third step of lifting the position (100) where the sub beam materials (20) are placed to a predetermined height with the forklift (200) and then rotating the turntable (110) by a predetermined angle such that the longitudinal direction of the sub beam materials (20) is parallel to the longitudinal direction of the space (11) of the main beam (10); a fourth step of completely lifting the position (100) with the forklift (200) such that the rotated sub beam materials (20) are positioned to be higher than the main beam (10); and a fifth step of re-rotating the sub beam materials (20) higher than the main beam (10) to the turntable (110) and lowering the sub beam materials (20) such that the sub beam materials (20) are hung in a transverse direction on the main beam (10) and lowering the position (100) to the floor. When the first to fifth steps are repeated with the position (100) lowered after the execution of the steps, the sub beam materials (20) can be more safely supplied. In addition, material supply can be expedited, and thus labor cost reduction can be achieved along with workability improvement and construction cost reduction.
본 발명은 클린룸의 이중마루 시스템 시공을 위해 일정 높이에 격자형으로 설치된 메인빔(10)의 여러 공간(11)을 통해 지게차(200)로 서브빔 자재를 공급하는 방법에 관한 것으로서, 리모컨 조작으로 회전하도록 턴테이블(110)이 설치된 포지션(100)을 구비하는 단계와; 메인빔(10)의 여러 공간(11) 중 한 곳의 바닥에 포지션(100)을 위치시키는 제1단계; 다단식 지게차(200)로 실어온 다수의 서브빔 자재(20)를 포지션(100)의 턴테이블(110) 위에 올려 안착하는 제2단계; 서브빔 자재(20)가 놓인 포지션(100)을 지게차(200)로 일정 높이 들어올린 후 서브빔 자재(20)의 길이방향이 메인빔(10)의 공간(11) 길이 방향과 평행하도록 턴테이블(110)을 일정 각도 회전시키는 제3단계; 상기 회전된 서브빔 자재(20)가 메인빔(10) 보다 높게 위치되도록 포지션(100)을 지게차(200)로 완전히 올리는 제4단계: 메인빔(10) 보다 높이 위치된 서브빔 자재(20)를 턴테이블(110)로 다시 회전시킨 후 내려서 메인빔(10)에 횡방향으로 걸쳐지게 하고, 포지션(100)은 바닥을 향해 하강시키는 제5단계; 를 행한 후 하강된 포지션(100)으로 상기 제1단계 부터 제5단계를 반복하면 서브빔 자재(20)를 종래보다 안전하게 공급할 수 있으며, 자재 공급이 신속하므로 인건비 절감과 작업성 향상으로 시공비를 낮출 수 있는 것이다.
Sub-beam materials for construction raised floor system supply of clean room way
클린룸의 이중마루 시스템 시공용 서브빔 자재 공급방법
CHO SANG WON (Autor:in)
10.12.2018
Patent
Elektronische Ressource
Koreanisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Module for clean room floor grating panel construction and clean room floor construction method
Europäisches Patentamt | 2024
|Anchor bar for clean room floor exhaust hole construction and clean room floor construction method
Europäisches Patentamt | 2024
|