CONSTRUCTION METHOD OF UNDERGROUND STRUCTURE USING THE TRENCHLESS INTERMEDIATE BASE
The present invention relates to a construction method for an underground structure with a long span, such as a long tunnel, using a trenchless method. The construction method for an underground structure, using the trenchless method, comprises: a step a) of constructing a first open cut base with an open upper part at a point which is out of a work section at intervals in the vertical direction from a trenchless intermediate base planned to divide the work section in which an underground structure is installed; a step b) of constructing the trenchless intermediate base of a tunnel shape, with the closed upper part, using the first open cut base; a step c) of constructing second and third open cut bases with the open upper part at both ends of the work section; a step d) of constructing a first underground structure by installing a tunnel structure between the trenchless intermediate base and the second open cut base; and a step e) of constructing a second underground structure by installing the tunnel structure between the trenchless intermediate base and the third open cut base.
본 발명은 비개착식 방법으로 장대터널과 같은 장구간의 지하구조물을 구축하는 방법으로서, a) 지하구조물이 설치되는 작업구간을 양분하도록 계획된 중간비개착기지로부터 수직한 방향으로 이격하여 작업구간을 벗어난 지점에 상부가 개방된 제1개착기지를 구축하는 단계; b) 상기 제1개착기지를 이용하여 상부가 폐쇄된 터널형의 중간비개착기지를 구축하는 단계; c) 상기 작업구간의 양 단부에 상부가 개방된 제2,3개착기지를 구축하는 단계; d) 중간비개착기지와 제2개착기지 사이에 터널구조물을 설치하여 제1지하구조물을 구축하는 단계; e) 중간비개착기지와 제3개착기지 사이에 터널구조물 설치하여 제2지하구조물을 구축하는 단계;가 포함되어 이루어지는 것을 특징으로 한다.
CONSTRUCTION METHOD OF UNDERGROUND STRUCTURE USING THE TRENCHLESS INTERMEDIATE BASE
The present invention relates to a construction method for an underground structure with a long span, such as a long tunnel, using a trenchless method. The construction method for an underground structure, using the trenchless method, comprises: a step a) of constructing a first open cut base with an open upper part at a point which is out of a work section at intervals in the vertical direction from a trenchless intermediate base planned to divide the work section in which an underground structure is installed; a step b) of constructing the trenchless intermediate base of a tunnel shape, with the closed upper part, using the first open cut base; a step c) of constructing second and third open cut bases with the open upper part at both ends of the work section; a step d) of constructing a first underground structure by installing a tunnel structure between the trenchless intermediate base and the second open cut base; and a step e) of constructing a second underground structure by installing the tunnel structure between the trenchless intermediate base and the third open cut base.
본 발명은 비개착식 방법으로 장대터널과 같은 장구간의 지하구조물을 구축하는 방법으로서, a) 지하구조물이 설치되는 작업구간을 양분하도록 계획된 중간비개착기지로부터 수직한 방향으로 이격하여 작업구간을 벗어난 지점에 상부가 개방된 제1개착기지를 구축하는 단계; b) 상기 제1개착기지를 이용하여 상부가 폐쇄된 터널형의 중간비개착기지를 구축하는 단계; c) 상기 작업구간의 양 단부에 상부가 개방된 제2,3개착기지를 구축하는 단계; d) 중간비개착기지와 제2개착기지 사이에 터널구조물을 설치하여 제1지하구조물을 구축하는 단계; e) 중간비개착기지와 제3개착기지 사이에 터널구조물 설치하여 제2지하구조물을 구축하는 단계;가 포함되어 이루어지는 것을 특징으로 한다.
CONSTRUCTION METHOD OF UNDERGROUND STRUCTURE USING THE TRENCHLESS INTERMEDIATE BASE
중간비개착기지를 이용한 지하구조물의 구축방법
KIM DONG SE (Autor:in) / KIM DONG SOO (Autor:in) / LEE JANGSIK (Autor:in) / PARK GEAN WOO (Autor:in)
24.09.2019
Patent
Elektronische Ressource
Koreanisch
Trenchless construction method of underground structures
Europäisches Patentamt | 2016
|Trenchless Construction for Underground Services
NTIS | 1987
|Underground : magazine for trenchless construction and microtunneling
TIBKAT | Nr. 1.1886 - 26.1992; 29.1992 - 35.1993; damit Ersch. eingest.
Trenchless Technology : the jewel of underground construction
TIBKAT | 1997
|Determination of geotechnical parameters for underground trenchless construction design
Springer Verlag | 2023
|