the Method of Construction of Prefabricated Block for Retaining Wall Bulwark
A method for constructing prefabricated blocks for a retaining wall comprises the steps of: forming a cut slope; forming a construction site on a base to install a block body; pouring concrete to form a foundation concrete layer on the construction site to support the block body; burying a plurality of fixing bolts at predetermined intervals in the foundation concrete layer; and fixing the fastening member of the block body and the fixing bolts by a connecting member to have a supporting force against the external force applied to a retaining wall structure. The fixing includes: hanging a hook formed at one end of the connecting member on the fastening member; and inserting the fixing bolts into fixing holes formed in the other end of the connecting member and fixing the block body. A step of completing the retaining wall structure by stacking the block body vertically and horizontally includes inclining the retaining wall structure at an angle of 5 degrees with respect to the foundation concrete layer in the direction of the cut slope. The stacking includes stacking the block body vertically and horizontally. The difference between the height (H1) of a left side of the block body and the height (H2) of a right side thereof is 5 mm, where H1 < H2.
본 발명의 옹벽용 조립식 블록의 시공방법은 절토사면지를 형성하는 단계; 블록본체를 설치할 수 있도록 기초부에 시공부지를 형성하는 단계; 블록본체를 지지하기 위하여 상기 시공부지 위에 기초콘크리트층을 형성하기 위해서 콘크리트를 타설하는 단계; 기초콘크리트층에 다수 개의 고정볼트를 소정의 간격으로 매설하는 단계; 상기 옹벽 구조물에 작용되는 외력에 대한 지지력을 갖도록 블록본체의 체결부재와 상기 고정볼트를 연결부재로 고정하는 단계를 포함하여 구성하되; 상기 옹벽 구조물에 작용되는 외력에 대한 지지력을 갖도록 블록본체의 체결부재와 고정볼트를 연결부재로 고정하는 단계는 상기 연결부재의 한쪽 끝단에 형성된 걸고리를 체결부재에 걸고, 상기 연결부재의 다른 끝단에 형성된 고정홀을 고정볼트에 끼우고 상기 블록본체를 고정시키고; 상기 블록본체를 상하 좌우로 적층하여 옹벽 구조물을 완성하는 단계는 절토사면지 방향으로 상기 옹벽 구조물이 기초콘크리트층과 5도 각도로 기울어게 하며, 상기 블록본체를 적층하는 단계는 상기 블록본체를 횡방향과 종방향으로 적층하는 단계이며; 상기 블록본체의 좌측면의 높이(H1)와 우측면의 높이(H2)는 5mm 차이가 나도록 하되, H1
the Method of Construction of Prefabricated Block for Retaining Wall Bulwark
A method for constructing prefabricated blocks for a retaining wall comprises the steps of: forming a cut slope; forming a construction site on a base to install a block body; pouring concrete to form a foundation concrete layer on the construction site to support the block body; burying a plurality of fixing bolts at predetermined intervals in the foundation concrete layer; and fixing the fastening member of the block body and the fixing bolts by a connecting member to have a supporting force against the external force applied to a retaining wall structure. The fixing includes: hanging a hook formed at one end of the connecting member on the fastening member; and inserting the fixing bolts into fixing holes formed in the other end of the connecting member and fixing the block body. A step of completing the retaining wall structure by stacking the block body vertically and horizontally includes inclining the retaining wall structure at an angle of 5 degrees with respect to the foundation concrete layer in the direction of the cut slope. The stacking includes stacking the block body vertically and horizontally. The difference between the height (H1) of a left side of the block body and the height (H2) of a right side thereof is 5 mm, where H1 < H2.
본 발명의 옹벽용 조립식 블록의 시공방법은 절토사면지를 형성하는 단계; 블록본체를 설치할 수 있도록 기초부에 시공부지를 형성하는 단계; 블록본체를 지지하기 위하여 상기 시공부지 위에 기초콘크리트층을 형성하기 위해서 콘크리트를 타설하는 단계; 기초콘크리트층에 다수 개의 고정볼트를 소정의 간격으로 매설하는 단계; 상기 옹벽 구조물에 작용되는 외력에 대한 지지력을 갖도록 블록본체의 체결부재와 상기 고정볼트를 연결부재로 고정하는 단계를 포함하여 구성하되; 상기 옹벽 구조물에 작용되는 외력에 대한 지지력을 갖도록 블록본체의 체결부재와 고정볼트를 연결부재로 고정하는 단계는 상기 연결부재의 한쪽 끝단에 형성된 걸고리를 체결부재에 걸고, 상기 연결부재의 다른 끝단에 형성된 고정홀을 고정볼트에 끼우고 상기 블록본체를 고정시키고; 상기 블록본체를 상하 좌우로 적층하여 옹벽 구조물을 완성하는 단계는 절토사면지 방향으로 상기 옹벽 구조물이 기초콘크리트층과 5도 각도로 기울어게 하며, 상기 블록본체를 적층하는 단계는 상기 블록본체를 횡방향과 종방향으로 적층하는 단계이며; 상기 블록본체의 좌측면의 높이(H1)와 우측면의 높이(H2)는 5mm 차이가 나도록 하되, H1
the Method of Construction of Prefabricated Block for Retaining Wall Bulwark
옹벽용 조립식 블록 시공방법
KIM JEONG SU (Autor:in)
14.06.2021
Patent
Elektronische Ressource
Koreanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Prefabricated retaining wall block and retaining wall construction method