Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Hydraulic Jack Module for Waterway Bridge Lifting and Restoration
The present invention relates to a bridge deck and pier lifting restoration method using a hydraulic jack module, allowing a bridge deck and piers to be easily lifted and restored using a hydraulic jack module installed on the bridge deck or piers, and managing the settlement, tilt, and behavior of the piers and bridge deck in real time using a position sensor after lifting and restoring the bridge deck and piers. The bridge deck and pier lifting restoration method using a hydraulic jack module comprises a vertical hole drilling step (S10), a lifting jig module installation step (S20), a support pile construction step (S30), a reaction force body module installation step (S40), a hydraulic jack module installation step (S50), a lifting step (S60), and a filling member construction step (S70) as main components.
본 발명은 유압잭모듈을 이용한 교량 상판 및 교각 인상 복원공법에 관련되며, 이는 교량상판 또는 교각에 설치한 유압잭모듈을 이용하여 교량상판 및 교각을 간단하게 인상 복원할 수 있고, 교량상판 및 교각을 인상 복원 후 위치센서를 이용하여 교각 및 교량상판의 침하, 기울기, 거동상태를 실시간으로 관리할 수 있도록 수직홀천공단계(S10), 인상지그모듈설치단계(S20), 버팀파일시공단계(S30), 반력체모듈설치단계(S40), 유압잭모듈설치단계(S50), 인상단계(S60), 채움부재시공단계(S70)를 포함하여 주요 구성으로 한다.
Hydraulic Jack Module for Waterway Bridge Lifting and Restoration
The present invention relates to a bridge deck and pier lifting restoration method using a hydraulic jack module, allowing a bridge deck and piers to be easily lifted and restored using a hydraulic jack module installed on the bridge deck or piers, and managing the settlement, tilt, and behavior of the piers and bridge deck in real time using a position sensor after lifting and restoring the bridge deck and piers. The bridge deck and pier lifting restoration method using a hydraulic jack module comprises a vertical hole drilling step (S10), a lifting jig module installation step (S20), a support pile construction step (S30), a reaction force body module installation step (S40), a hydraulic jack module installation step (S50), a lifting step (S60), and a filling member construction step (S70) as main components.
본 발명은 유압잭모듈을 이용한 교량 상판 및 교각 인상 복원공법에 관련되며, 이는 교량상판 또는 교각에 설치한 유압잭모듈을 이용하여 교량상판 및 교각을 간단하게 인상 복원할 수 있고, 교량상판 및 교각을 인상 복원 후 위치센서를 이용하여 교각 및 교량상판의 침하, 기울기, 거동상태를 실시간으로 관리할 수 있도록 수직홀천공단계(S10), 인상지그모듈설치단계(S20), 버팀파일시공단계(S30), 반력체모듈설치단계(S40), 유압잭모듈설치단계(S50), 인상단계(S60), 채움부재시공단계(S70)를 포함하여 주요 구성으로 한다.
Hydraulic Jack Module for Waterway Bridge Lifting and Restoration
유압잭모듈을 이용한 교량 상판 및 교각 인상 복원공법
KIM YOUNG WOON (Autor:in) / PARK BUM KU (Autor:in)
17.10.2023
Patent
Elektronische Ressource
Koreanisch
IPC:
E01D
BRIDGES
,
Brücken
/
B66F
HOISTING, LIFTING, HAULING, OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
,
Hub-, Verhol- oder Schubvorrichtungen, soweit nicht anderweitig vorgesehen, z.B. Vorrichtungen mit unmittelbarer Krafteinwirkung auf die Last
/
G01D
MEASURING NOT SPECIALLY ADAPTED FOR A SPECIFIC VARIABLE
,
Anzeigen oder Aufzeichnen in Verbindung mit Messen allgemein
/
G06Q
Datenverarbeitungssysteme oder -verfahren, besonders angepasst an verwaltungstechnische, geschäftliche, finanzielle oder betriebswirtschaftliche Zwecke, sowie an geschäftsbezogene Überwachungs- oder Voraussagezwecke
,
DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES
Europäisches Patentamt | 2017
|Elastic hydraulic jack for precision lift of bridge and bridge lifting method using the same
Europäisches Patentamt | 2021
|Europäisches Patentamt | 2017
|