CONNECTION METHOD OF CONCRETE FILLED TUBE BRIDGE COLUMN AND REINFORCED CONCRETE FOOTING
The present invention relates to a connection method between a concrete-filled steel pipe bridge pier pillar and a ferroconcrete base. More specifically, the present invention relates to a connection method between a concrete-filled steel pipe bridge pier pillar and a ferroconcrete base, which is able to radially arrange a plurality of pillar main rebars and embed the pillar main rebars to protrude vertically when placing the ferroconcrete base, embed strap rebars on an outer side of the pillar main rebars, insert a concrete-filled steel pipe bridge pier pillar of a unit module into the pillar main rebars, install a formwork on the outer side of the pillar main rebars, and place concrete so that the pillar main rebars, the concrete-filled steel pipe bridge pier pillar, and the ferroconcrete base can be integrated with each other. Therefore, the construction interference between the ferroconcrete base and the concrete-filled steel pipe pillars can be prevented, and the resistance ability of the concrete-filled steel pipe bridge pier pillar can be improved.
본 발명은 충전강관 교각 기둥과 철근 콘크리트 기초간의 연결 공법에 관한 것으로서, 상세하게는 철근 콘크리트 기초 타설시 복수의 기둥 주철근이 방사상으로 배치되어 수직으로 돌출되도록 매립하고, 기둥 주철근 외측으로 띠철근을 배근하며, 기둥 주철근 내부에 단위모듈의 충전강관 교각 기둥을 삽입한 다음, 기둥 주철근 외측에 거푸집을 설치한 다음 기둥 주철근과 충전강관 교각 기둥이 철근 콘크리트 기초와 일체화되도록 콘크리트를 타설함으로써 철근 콘크리트 기초와 충전강관 기둥의 시공 간섭을 배제하고, 충전강관 교각 기둥의 저항능력을 향상시키도록 하는 충전강관 교각 기둥과 철근 콘크리트 기초간의 연결 공법에 관한 것이다.
CONNECTION METHOD OF CONCRETE FILLED TUBE BRIDGE COLUMN AND REINFORCED CONCRETE FOOTING
The present invention relates to a connection method between a concrete-filled steel pipe bridge pier pillar and a ferroconcrete base. More specifically, the present invention relates to a connection method between a concrete-filled steel pipe bridge pier pillar and a ferroconcrete base, which is able to radially arrange a plurality of pillar main rebars and embed the pillar main rebars to protrude vertically when placing the ferroconcrete base, embed strap rebars on an outer side of the pillar main rebars, insert a concrete-filled steel pipe bridge pier pillar of a unit module into the pillar main rebars, install a formwork on the outer side of the pillar main rebars, and place concrete so that the pillar main rebars, the concrete-filled steel pipe bridge pier pillar, and the ferroconcrete base can be integrated with each other. Therefore, the construction interference between the ferroconcrete base and the concrete-filled steel pipe pillars can be prevented, and the resistance ability of the concrete-filled steel pipe bridge pier pillar can be improved.
본 발명은 충전강관 교각 기둥과 철근 콘크리트 기초간의 연결 공법에 관한 것으로서, 상세하게는 철근 콘크리트 기초 타설시 복수의 기둥 주철근이 방사상으로 배치되어 수직으로 돌출되도록 매립하고, 기둥 주철근 외측으로 띠철근을 배근하며, 기둥 주철근 내부에 단위모듈의 충전강관 교각 기둥을 삽입한 다음, 기둥 주철근 외측에 거푸집을 설치한 다음 기둥 주철근과 충전강관 교각 기둥이 철근 콘크리트 기초와 일체화되도록 콘크리트를 타설함으로써 철근 콘크리트 기초와 충전강관 기둥의 시공 간섭을 배제하고, 충전강관 교각 기둥의 저항능력을 향상시키도록 하는 충전강관 교각 기둥과 철근 콘크리트 기초간의 연결 공법에 관한 것이다.
CONNECTION METHOD OF CONCRETE FILLED TUBE BRIDGE COLUMN AND REINFORCED CONCRETE FOOTING
충전강관 교각 기둥과 철근 콘크리트 기초간의 연결 공법
MA HYANG WOOK (Autor:in) / SHIN YOON BONG (Autor:in) / KIM SANG HYUN (Autor:in) / BAE SUNG WOON (Autor:in)
21.12.2023
Patent
Elektronische Ressource
Koreanisch
CONNECTION METHOD OF CONCRETE FILLED TUBE BRIDGE COLUMN AND REINFORCED CONCRETE PIER CAP
Europäisches Patentamt | 2023
|Concrete-filled steel tube column-reinforced concrete beam joint connection method
Europäisches Patentamt | 2015
|Concrete-filled fiber reinforced polymer tube-footing interaction in bending
British Library Conference Proceedings | 2008
|CONNECTION OF CONCRETE-FILLED STEEL TUBE COLUMN AND REINFORCED CONCRETE SLAB
Europäisches Patentamt | 2020
|CONNECTION OF CONCRETE-FILLED STEEL TUBE COLUMN AND REINFORCED CONCRETE SLAB
Europäisches Patentamt | 2020
|