Method for constructing fixed monitoring pile for mining area with high phreatic water level
A method for constructing a fixed monitoring pile for a mining area with a high phreatic water level includes: S1: prefabricating a pile foundation body, where the pile foundation body has a columnar structure, and a plurality of extension connection ports are provided at an outer side and a bottom of the pile foundation body; and S2: digging a foundation pit at a designated monitoring point; combining the pile foundation body with an extension body to form a fixed monitoring pile; placing the fixed monitoring pile into the foundation pit, such that a bottom extension body and a side extension body are inserted into the pit foundation; and backfilling and compacting. The method increases the affinity between the fixed monitoring pile and a loose layer and strengthens the fixed monitoring pile to prevent it from loosening, thereby improving measurement accuracy.
Method for constructing fixed monitoring pile for mining area with high phreatic water level
A method for constructing a fixed monitoring pile for a mining area with a high phreatic water level includes: S1: prefabricating a pile foundation body, where the pile foundation body has a columnar structure, and a plurality of extension connection ports are provided at an outer side and a bottom of the pile foundation body; and S2: digging a foundation pit at a designated monitoring point; combining the pile foundation body with an extension body to form a fixed monitoring pile; placing the fixed monitoring pile into the foundation pit, such that a bottom extension body and a side extension body are inserted into the pit foundation; and backfilling and compacting. The method increases the affinity between the fixed monitoring pile and a loose layer and strengthens the fixed monitoring pile to prevent it from loosening, thereby improving measurement accuracy.
Method for constructing fixed monitoring pile for mining area with high phreatic water level
LI HAO (Autor:in) / AN SHIKAI (Autor:in) / HAN BIWU (Autor:in) / GUO HONGXING (Autor:in) / XU YANFEI (Autor:in) / YU YUNFEI (Autor:in) / LIAO QINGFA (Autor:in) / ZHAO DERONG (Autor:in) / MIAO WEI (Autor:in)
07.01.2025
Patent
Elektronische Ressource
Englisch
Farmland Damage and Treatment Status in Coal Mining Subsidence Area with High Phreatic Water Level
British Library Conference Proceedings | 2014
|Experiments on Evaporation of High-TDS Phreatic Water in an Arid Area
British Library Conference Proceedings | 2012
|Estimation of multi-well dewatering induced pile foundation settlement in phreatic zones
British Library Conference Proceedings | 2007
|Impact of mining subsidence on phreatic environment and its ramification
British Library Online Contents | 1999
|