Disclosed is a slab lowering construction method for an underground structure in a reverse construction method, comprising the following steps: first constructing underground guide grooves and underground diaphragm walls, then constructing upright post piles, installing a crane frame and a crane, and placing precast beam slabs in which each layer is of an integral structure in a superimposed manner and fixing same by means of the crane; and then, sequentially lowering the precast beam slabs layer by layer by means of the crane to complete the construction of all the precast beam slabs. During the lowering process of the precast beam slabs, a plurality of pairs of laser range finders and targets provided on vertically adjacent precast beam slabs monitor whether the precast beam slabs are inclined, and a control terminal controls a servo mechanism of the crane to adjust the lowering speed of the crane, thereby ensuring that the precast beam slabs are lowered stably. According to the construction method, a reverse slab lowering construction technology is combined with a prefabricated construction technology, and therefore, the construction is easy and convenient, and is more efficient, stable and safe, and the construction equality is ensured.
Procédé de construction par abaissement de dalle pour une structure souterraine dans un procédé de construction inverse, comprenant les étapes suivantes consistant à : tout d'abord construire des rainures de guidage souterraines et des parois de diaphragme souterraines, puis construire des pieux de montant verticaux, installer un cadre de grue et une grue, et placer des dalles de poutre prémoulées dans lesquelles chaque couche est d'une structure intégrale d'une manière superposée et les fixer au moyen de la grue ; puis abaisser séquentiellement les dalles de poutre prémoulées par couche au moyen de la grue pour achever la construction de toutes les dalles de poutre prémoulées. Pendant le processus d'abaissement des dalles de poutre prémoulées, une pluralité de paires de télémètres laser et de cibles disposés sur des dalles de poutre prémoulées verticalement adjacentes surveillent si les dalles de poutre prémoulées sont inclinées, et une borne de commande commande un servomécanisme de la grue pour ajuster la vitesse d'abaissement de la grue, ce qui permet de s'assurer que les dalles de poutre prémoulées sont abaissées de manière stable. Selon le procédé de construction, une technologie de construction par abaissement de dalle inverse est combinée à une technologie de construction préfabriquée, et par conséquent, la construction est facile et pratique, et est plus efficace, stable et sûre, et l'égalité de construction est assurée.
本发明公开了一种逆作法中地下结构的降板施工方法,包括如下步骤:先施工地下导槽和地下连续墙,然后施工立柱桩,安装吊机架及吊机,将每一层均为整体结构的预制梁板叠合放置,通过吊机固定;然后通过吊机依次逐层下放预制梁板,完成所有预制梁板的施工,在预制梁板下放过程中,通过设置于上下相邻的预制梁板上的多对激光测距仪和标靶,监测预制梁板是否倾斜,通过控制终端控制吊机的伺服机构,调整吊机的下降速率,从而保证预制梁板平稳下降。采用该施工方法,将逆作降板法施工技术与预制装配式施工技术相结合,施工简便且更加高效、稳定、安全,保障了施工质量。
Disclosed is a slab lowering construction method for an underground structure in a reverse construction method, comprising the following steps: first constructing underground guide grooves and underground diaphragm walls, then constructing upright post piles, installing a crane frame and a crane, and placing precast beam slabs in which each layer is of an integral structure in a superimposed manner and fixing same by means of the crane; and then, sequentially lowering the precast beam slabs layer by layer by means of the crane to complete the construction of all the precast beam slabs. During the lowering process of the precast beam slabs, a plurality of pairs of laser range finders and targets provided on vertically adjacent precast beam slabs monitor whether the precast beam slabs are inclined, and a control terminal controls a servo mechanism of the crane to adjust the lowering speed of the crane, thereby ensuring that the precast beam slabs are lowered stably. According to the construction method, a reverse slab lowering construction technology is combined with a prefabricated construction technology, and therefore, the construction is easy and convenient, and is more efficient, stable and safe, and the construction equality is ensured.
Procédé de construction par abaissement de dalle pour une structure souterraine dans un procédé de construction inverse, comprenant les étapes suivantes consistant à : tout d'abord construire des rainures de guidage souterraines et des parois de diaphragme souterraines, puis construire des pieux de montant verticaux, installer un cadre de grue et une grue, et placer des dalles de poutre prémoulées dans lesquelles chaque couche est d'une structure intégrale d'une manière superposée et les fixer au moyen de la grue ; puis abaisser séquentiellement les dalles de poutre prémoulées par couche au moyen de la grue pour achever la construction de toutes les dalles de poutre prémoulées. Pendant le processus d'abaissement des dalles de poutre prémoulées, une pluralité de paires de télémètres laser et de cibles disposés sur des dalles de poutre prémoulées verticalement adjacentes surveillent si les dalles de poutre prémoulées sont inclinées, et une borne de commande commande un servomécanisme de la grue pour ajuster la vitesse d'abaissement de la grue, ce qui permet de s'assurer que les dalles de poutre prémoulées sont abaissées de manière stable. Selon le procédé de construction, une technologie de construction par abaissement de dalle inverse est combinée à une technologie de construction préfabriquée, et par conséquent, la construction est facile et pratique, et est plus efficace, stable et sûre, et l'égalité de construction est assurée.
本发明公开了一种逆作法中地下结构的降板施工方法,包括如下步骤:先施工地下导槽和地下连续墙,然后施工立柱桩,安装吊机架及吊机,将每一层均为整体结构的预制梁板叠合放置,通过吊机固定;然后通过吊机依次逐层下放预制梁板,完成所有预制梁板的施工,在预制梁板下放过程中,通过设置于上下相邻的预制梁板上的多对激光测距仪和标靶,监测预制梁板是否倾斜,通过控制终端控制吊机的伺服机构,调整吊机的下降速率,从而保证预制梁板平稳下降。采用该施工方法,将逆作降板法施工技术与预制装配式施工技术相结合,施工简便且更加高效、稳定、安全,保障了施工质量。
SLAB LOWERING CONSTRUCTION METHOD FOR UNDERGROUND STRUCTURE IN REVERSE CONSTRUCTION METHOD
PROCÉDÉ DE CONSTRUCTION PAR ABAISSEMENT DE DALLE POUR STRUCTURE SOUTERRAINE DANS UN PROCÉDÉ DE CONSTRUCTION INVERSE
逆作法中地下结构的降板施工方法
25.02.2021
Patent
Elektronische Ressource
Chinesisch
Beam lowering construction method for underground structure in reverse construction method
Europäisches Patentamt | 2020
|Europäisches Patentamt | 2015
|UNDERGROUND SLAB STRUCTURE AND UNDERGROUND CONSTRUCTION METHOD USING THE SAME
Europäisches Patentamt | 2017
|Underground engineering foundation slab structure and construction method thereof
Europäisches Patentamt | 2020