PLASTIC CASING SECANT PILE CONSTRUCTION METHOD
Provided is a plastic casing secant pile construction method, the steps being: (1) constructing first pile holes (11, 12, 13) at intervals; (2) lowering a first steel reinforcing cage (31) carrying a first plastic hollow pipe (32) into the first pile holes (11, 12, 13), and pouring sand into the first plastic hollow pipe (32); pouring concrete into the first pile holes (11, 12, 13) to form a first pile body (39); (3) constructing a second pile hole (21, 22) between the adjacent first pile holes (11, 12, 13); (4) lowering a second steel reinforcing cage (41) carrying a second plastic hollow pipe (42) into the second pile holes (21, 22), and pouring sand into the second plastic hollow pipe (42); then pouring concrete into the second pile holes (21, 22) to form a second pile body (49); (5) hole-drilling between the adjacent first pile body (39) and second pile body (49) using a high-pressure rotary jet drill, and spraying cement slurry to form a cement mortar (50), said cement mortar (50) connecting the adjacent first pile body (39) and the second pile body (49) as one body.
L'invention concerne un procédé de construction de pieux sécants à enveloppe en plastique, les étapes consistent à : (1) Construire des premiers trous de pieux (11, 12, 13) à des intervalles ; (2) faire descendre une première cage de renforcement en acier (31) portant une première conduite creuse en plastique (32) dans les premiers trous de pieux (11, 12, 13), et verser du sable dans la première conduite creuse en plastique (32) ; couler du béton dans les premiers trous de pieux (11, 12, 13) pour former un premier corps de pieu (39) ; (3) construire un second trou de pieu (21, 22) entre les premiers trous de pieux adjacents (11, 12, 13) ; (4) faire descendre une seconde cage de renforcement en acier (41) portant une seconde conduite creuse en plastique (42) dans les seconds trous de pieux (21, 22), et verser du sable dans la seconde conduite creuse en plastique (42) ; couler du béton dans les seconds trous de pieux (21, 22) pour former un second corps de pieu (49) ; (5) réaliser des trous de forage entre le premier corps de pieu adjacent (39) et un second corps de pieu (49) à l'aide d'un foret à jet rotatif haute pression, et pulvériser un laitier de ciment pour former un mortier de ciment (50), ledit mortier de ciment (50) reliant le premier corps de pieu adjacent (39) et le second corps de pieu (49) en tant qu'un seul corps.
一种塑料套管咬合桩的施工方法,步骤为:(1)间隔施工第一桩孔(11、12、13);(2)将携带第一塑料空心管(32)的第一钢筋笼(31)下放到第一桩孔(11、12、13)内,在第一塑料空心管(32)内灌入砂子;在第一桩孔(11、12、13)内浇注混凝土,形成第一桩体(39);(3)在相邻的第一桩孔(11、12、13)之间施工第二桩孔(21、22);(4)将携带第二塑料空心管(42)的第二钢筋笼(41)下放到第二桩孔(21、22)内,在第二塑料空心管(42)内灌入砂子;然后在第二桩孔(21、22)内浇注混凝土,形成第二桩体(49);(5)在相邻第一桩体(39)与第二桩体(49)之间采用高压旋喷钻进行钻孔,并喷射水泥浆,形成水泥砂浆(50),该水泥砂浆(50)将相邻的第一桩体(39)和第二桩体(49)连接为一体。
PLASTIC CASING SECANT PILE CONSTRUCTION METHOD
Provided is a plastic casing secant pile construction method, the steps being: (1) constructing first pile holes (11, 12, 13) at intervals; (2) lowering a first steel reinforcing cage (31) carrying a first plastic hollow pipe (32) into the first pile holes (11, 12, 13), and pouring sand into the first plastic hollow pipe (32); pouring concrete into the first pile holes (11, 12, 13) to form a first pile body (39); (3) constructing a second pile hole (21, 22) between the adjacent first pile holes (11, 12, 13); (4) lowering a second steel reinforcing cage (41) carrying a second plastic hollow pipe (42) into the second pile holes (21, 22), and pouring sand into the second plastic hollow pipe (42); then pouring concrete into the second pile holes (21, 22) to form a second pile body (49); (5) hole-drilling between the adjacent first pile body (39) and second pile body (49) using a high-pressure rotary jet drill, and spraying cement slurry to form a cement mortar (50), said cement mortar (50) connecting the adjacent first pile body (39) and the second pile body (49) as one body.
L'invention concerne un procédé de construction de pieux sécants à enveloppe en plastique, les étapes consistent à : (1) Construire des premiers trous de pieux (11, 12, 13) à des intervalles ; (2) faire descendre une première cage de renforcement en acier (31) portant une première conduite creuse en plastique (32) dans les premiers trous de pieux (11, 12, 13), et verser du sable dans la première conduite creuse en plastique (32) ; couler du béton dans les premiers trous de pieux (11, 12, 13) pour former un premier corps de pieu (39) ; (3) construire un second trou de pieu (21, 22) entre les premiers trous de pieux adjacents (11, 12, 13) ; (4) faire descendre une seconde cage de renforcement en acier (41) portant une seconde conduite creuse en plastique (42) dans les seconds trous de pieux (21, 22), et verser du sable dans la seconde conduite creuse en plastique (42) ; couler du béton dans les seconds trous de pieux (21, 22) pour former un second corps de pieu (49) ; (5) réaliser des trous de forage entre le premier corps de pieu adjacent (39) et un second corps de pieu (49) à l'aide d'un foret à jet rotatif haute pression, et pulvériser un laitier de ciment pour former un mortier de ciment (50), ledit mortier de ciment (50) reliant le premier corps de pieu adjacent (39) et le second corps de pieu (49) en tant qu'un seul corps.
一种塑料套管咬合桩的施工方法,步骤为:(1)间隔施工第一桩孔(11、12、13);(2)将携带第一塑料空心管(32)的第一钢筋笼(31)下放到第一桩孔(11、12、13)内,在第一塑料空心管(32)内灌入砂子;在第一桩孔(11、12、13)内浇注混凝土,形成第一桩体(39);(3)在相邻的第一桩孔(11、12、13)之间施工第二桩孔(21、22);(4)将携带第二塑料空心管(42)的第二钢筋笼(41)下放到第二桩孔(21、22)内,在第二塑料空心管(42)内灌入砂子;然后在第二桩孔(21、22)内浇注混凝土,形成第二桩体(49);(5)在相邻第一桩体(39)与第二桩体(49)之间采用高压旋喷钻进行钻孔,并喷射水泥浆,形成水泥砂浆(50),该水泥砂浆(50)将相邻的第一桩体(39)和第二桩体(49)连接为一体。
PLASTIC CASING SECANT PILE CONSTRUCTION METHOD
PROCÉDÉ DE CONSTRUCTION DE PIEUX SÉCANTS À ENVELOPPE EN PLASTIQUE
塑料套管咬合桩的施工方法
LI RENMIN (Autor:in) / WANG JIANLAN (Autor:in) / CHEN JING (Autor:in) / WANG TAO (Autor:in) / LIU XIAOBO (Autor:in)
30.06.2022
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
All-casing pore-forming secant pile construction method
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2021
|Casing pipe construction equipment for all casing pipe secant pile and method using same
Europäisches Patentamt | 2020
|