CONSTRUCTION METHOD FOR RAPIDLY DRIVING TRESTLE STEEL PIPE PILE INTO SLOPED BARE ROCK
Provided in the present invention is a construction method for rapidly driving a trestle steel pipe pile into sloped bare rock. The construction method comprises the steps: (1) mounting a cantilever Bailey platform; (2) mounting universal beams; (3) mounting and fixing a steel casing; (4) mounting a drilling rig and punching a hole; (5) feeding and lengthening the steel casing; (6) forming the hole; (7) filling the hole with bagged cement or bagged concrete dry material; (8) pulling out the casing, and removing a drilling rig; and (9) inserting and impacting the steel pipe pile for piling: driving the steel pipe pile, repeatedly impacting and lifting same for several times so as to cause the cement or dry material in the hole to fully react with water, and anchoring a pile tip to complete piling construction on the bare rock. In the present invention, a restraint frame for suspension of the casing and the drilling rig are installed by taking an extension cantilever structure formed by an overpass trestle as a drilling platform, and arrangement of an auxiliary drilling platform or usage of a floating pile driver are not needed, thus reducing construction procedures and engineering costs.
La présente invention concerne un procédé de construction pour entraîner rapidement un pilier chevalet en tube en acier dans une roche nue inclinée. Le procédé de construction comprend les étapes consistant à : (1) monter une plate-forme Bailey en porte-à-faux ; (2) monter des poutres universelles ; (3) monter et fixer un boîtier en acier ; (4) monter un appareil de forage et perforer un trou ; (5) alimenter et allonger le boîtier en acier ; (6) former le trou ; (7) remplir le trou avec du ciment ensaché ou un matériau sec en béton ensaché ; (8) tirer le boîtier, et retirer un appareil de forage ; et (9) insérer et impacter le pilier en tube en acier pour l'empilement : entraîner le pilier en tube en acier, impacter et soulever de manière répétée celui-ci plusieurs fois de façon à amener le ciment ou le matériau sec dans le trou à réagir complètement avec de l'eau, et ancrer une pointe de pilier pour achever la construction d'empilement sur la roche nue. Dans la présente invention, un cadre de retenue pour la suspension du boîtier et de l'appareil de forage est installé en prenant une structure en porte-à-faux d'extension formée par un chevalet passerelle en tant que plate-forme de forage, et l'agencement d'une plate-forme de forage auxiliaire ou l'utilisation d'un dispositif d'entraînement de pilier flottant n'est pas nécessaire, ce qui permet de réduire les procédures de construction et les coûts d'ingénierie.
本发明提供一种斜基面裸岩上栈桥钢管桩快速植桩工法,该工法包括步骤:(1)悬臂贝雷平台安装;(2)安装工字钢;(3)钢护筒安装及固定;(4)安装钻机冲孔;(5)钢护筒跟进接长;(6)成孔;(7)孔内填袋装水泥或袋装砼干料;(8)护筒拔除、移除钻机;(9)插打钢管桩植桩:打入钢管桩,并上下反复冲拔数次,让孔内的水泥或者干料能与水分充分反应,锚固桩端,完成裸岩植桩施工。本发明利用上跨栈桥形成的延伸悬臂结构作钻孔平台,安装悬吊护筒的限位架和钻机,无需搭设辅助钻孔平台或采用打桩船,减少了施工环节,降低了工程成本。
CONSTRUCTION METHOD FOR RAPIDLY DRIVING TRESTLE STEEL PIPE PILE INTO SLOPED BARE ROCK
Provided in the present invention is a construction method for rapidly driving a trestle steel pipe pile into sloped bare rock. The construction method comprises the steps: (1) mounting a cantilever Bailey platform; (2) mounting universal beams; (3) mounting and fixing a steel casing; (4) mounting a drilling rig and punching a hole; (5) feeding and lengthening the steel casing; (6) forming the hole; (7) filling the hole with bagged cement or bagged concrete dry material; (8) pulling out the casing, and removing a drilling rig; and (9) inserting and impacting the steel pipe pile for piling: driving the steel pipe pile, repeatedly impacting and lifting same for several times so as to cause the cement or dry material in the hole to fully react with water, and anchoring a pile tip to complete piling construction on the bare rock. In the present invention, a restraint frame for suspension of the casing and the drilling rig are installed by taking an extension cantilever structure formed by an overpass trestle as a drilling platform, and arrangement of an auxiliary drilling platform or usage of a floating pile driver are not needed, thus reducing construction procedures and engineering costs.
La présente invention concerne un procédé de construction pour entraîner rapidement un pilier chevalet en tube en acier dans une roche nue inclinée. Le procédé de construction comprend les étapes consistant à : (1) monter une plate-forme Bailey en porte-à-faux ; (2) monter des poutres universelles ; (3) monter et fixer un boîtier en acier ; (4) monter un appareil de forage et perforer un trou ; (5) alimenter et allonger le boîtier en acier ; (6) former le trou ; (7) remplir le trou avec du ciment ensaché ou un matériau sec en béton ensaché ; (8) tirer le boîtier, et retirer un appareil de forage ; et (9) insérer et impacter le pilier en tube en acier pour l'empilement : entraîner le pilier en tube en acier, impacter et soulever de manière répétée celui-ci plusieurs fois de façon à amener le ciment ou le matériau sec dans le trou à réagir complètement avec de l'eau, et ancrer une pointe de pilier pour achever la construction d'empilement sur la roche nue. Dans la présente invention, un cadre de retenue pour la suspension du boîtier et de l'appareil de forage est installé en prenant une structure en porte-à-faux d'extension formée par un chevalet passerelle en tant que plate-forme de forage, et l'agencement d'une plate-forme de forage auxiliaire ou l'utilisation d'un dispositif d'entraînement de pilier flottant n'est pas nécessaire, ce qui permet de réduire les procédures de construction et les coûts d'ingénierie.
本发明提供一种斜基面裸岩上栈桥钢管桩快速植桩工法,该工法包括步骤:(1)悬臂贝雷平台安装;(2)安装工字钢;(3)钢护筒安装及固定;(4)安装钻机冲孔;(5)钢护筒跟进接长;(6)成孔;(7)孔内填袋装水泥或袋装砼干料;(8)护筒拔除、移除钻机;(9)插打钢管桩植桩:打入钢管桩,并上下反复冲拔数次,让孔内的水泥或者干料能与水分充分反应,锚固桩端,完成裸岩植桩施工。本发明利用上跨栈桥形成的延伸悬臂结构作钻孔平台,安装悬吊护筒的限位架和钻机,无需搭设辅助钻孔平台或采用打桩船,减少了施工环节,降低了工程成本。
CONSTRUCTION METHOD FOR RAPIDLY DRIVING TRESTLE STEEL PIPE PILE INTO SLOPED BARE ROCK
PROCÉDÉ DE CONSTRUCTION POUR ENTRAÎNER RAPIDEMENT UN PILIER CHEVALET EN TUBE EN ACIER DANS UNE ROCHE NUE INCLINÉE
一种斜基面裸岩上栈桥钢管桩快速植桩工法
DANG YANJUN (Autor:in) / ZHAO RUI (Autor:in) / ZHOU HUANFENG (Autor:in) / FU QINGSONG (Autor:in) / WANG YINBIAO (Autor:in) / PENG JIE (Autor:in) / LIN JUNCHEN (Autor:in) / LIU MENGYANG (Autor:in) / YAN XIYUAN (Autor:in) / JIANG HUANGMING (Autor:in)
02.11.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Anchor pile construction method on bare rock foundation of steel trestle
Europäisches Patentamt | 2024
|Rock-socketed miniature steel pipe pile trestle foundation construction method
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2024
|Bare rock riverbed steel trestle and construction method thereof
Europäisches Patentamt | 2021
|Europäisches Patentamt | 2024
|