Turbine Performance Test - Unit G24. Grand Coulee Dam, Grand Coulee Third Powerplant, Columbia Basin Project. Flow Measurement by the Pressure-time Method
A performance test was conducted June 7 to 9, 1983, on the vertical-shaft, Francis turbine at Grand Coulee Third Powerplant, Grand Coulee Dam, Washington. Operating characteristics were determined: i.e., horsepower, discharge, efficiency, and flow index calibrations.
Turbine Performance Test - Unit G24. Grand Coulee Dam, Grand Coulee Third Powerplant, Columbia Basin Project. Flow Measurement by the Pressure-time Method
A performance test was conducted June 7 to 9, 1983, on the vertical-shaft, Francis turbine at Grand Coulee Third Powerplant, Grand Coulee Dam, Washington. Operating characteristics were determined: i.e., horsepower, discharge, efficiency, and flow index calibrations.
Turbine Performance Test - Unit G24. Grand Coulee Dam, Grand Coulee Third Powerplant, Columbia Basin Project. Flow Measurement by the Pressure-time Method
L. Heigel (Autor:in) / A. B. Lewey (Autor:in) / J. P. Favero (Autor:in)
1984
67 pages
Report
Keine Angabe
Englisch
Electric Power Production , Turbogenerators , Electric power plants , Hydraulic turbines , Data , Pressure measurement , Power measurement , Flow measurement , Performance tests , Efficiency , Discharge , Hydroelectric power generation , Hydroelectric generators , Grand Coulee Third Powerplant(Washington)
Structural design -- Grand Coulee third powerplant
Engineering Index Backfile | 1968
|Engineering Index Backfile | 1942
Engineering Index Backfile | 1938
SPECIAL REPORT: Grand Coulee Dam - Improving the Performance of Grand Coulee Equipment
Online Contents | 2001
|Columbia river highway bridge at grand coulee dam, Columbia basin project, Washington
Engineering Index Backfile | 1934