Sawmill Hydrostation Redevelopment. First Annual Report
Progress during the period from July 1979 to July 1980 in the redevelopment of the Sawmill Dam in New Hampshire as a run-of-river hydroelectric generating station is reported. This project should demonstrate the technical and economic feasibility of retrofitting existing dams for low-head hydro power plants. The topics discussed include licensing and permits, project planning, environmental concerns, engineering and design, safety, materials and equipment procurement, publicity, and construction status. (ERA citation 06:013584)
Sawmill Hydrostation Redevelopment. First Annual Report
Progress during the period from July 1979 to July 1980 in the redevelopment of the Sawmill Dam in New Hampshire as a run-of-river hydroelectric generating station is reported. This project should demonstrate the technical and economic feasibility of retrofitting existing dams for low-head hydro power plants. The topics discussed include licensing and permits, project planning, environmental concerns, engineering and design, safety, materials and equipment procurement, publicity, and construction status. (ERA citation 06:013584)
Sawmill Hydrostation Redevelopment. First Annual Report
1980
56 pages
Report
Keine Angabe
Englisch
Hydrostation reservoirs and recreation
Springer Verlag | 1990
|Hydrostation reservoirs and recreation
Online Contents | 1990
|Strength of hydrostation trash rack bars
Online Contents | 1985
|Monitoring the clogging of hydrostation trash racks
Online Contents | 1988
|Provision of strength of hydrostation trash racks
Online Contents | 1985
|