National Transportation Safety Board Highway Accident Report: Collapse of I-35W Highway Bridge, Minneapolis, Minnesota, on August 1, 2007
About 6:05 p.m. central daylight time on Wednesday, August 1, 2007, the eight-lane, 1,907-foot long I-35W highway bridge over the Mississippi River in Minneapolis, Minnesota, experienced a catastrophic failure in the main span of the deck truss. As a result, 1,000 feet of the deck truss collapsed, with about 456 feet of the main span falling 108 feet into the 15-foot deep river. A total of 111 vehicles were on the portion of the bridge that collapsed. Of these, 17 were recovered from the water. As a result of the bridge collapse, 13 people died, and 145 people were injured. On the day of the collapse, roadway work was underway on the I-35W bridge, and four of the eight travel lanes (two outside lanes northbound and two inside lanes southbound) were closed to traffic. In the early afternoon, construction equipment and construction aggregates (sand and gravel for making concrete) were delivered and positioned in the two closed inside southbound lanes. The equipment and aggregates, which were being staged for a concrete pour of the southbound lanes that was to begin about 7:00 p.m., were positioned toward the south end of the center section of the deck truss portion of the bridge and were in place by about 2:30 p.m. About 6:05 p.m., a motion-activated surveillance video camera at the Lower St. Anthony Falls Lock and Dam, just west of the I-35W bridge, recorded a portion of the collapse sequence. The video showed the bridge center span separating from the rest of the bridge and falling into the river. Major safety issues identified in this investigation include insufficient bridge design firm quality control procedures for designing bridges, and insufficient Federal and State procedures for reviewing and approving bridge design plans and calculations; lack of guidance for bridge owners with regard to the placement of construction loads on bridges during repair or maintenance activities; exclusion of gusset plates in bridge load rating guidance; lack of inspection guidance for conditions of gusset plate distortion; and inadequate use of technologies for accurately assessing the condition of gusset plates on deck truss bridges. As a result of this accident investigation, the Safety Board makes recommendations to the Federal Highway Administration (FHWA) and the American Association of State Highway and Transportation Officials. One safety recommendation resulting from this investigation was issued to the FHWA in January 2008.
National Transportation Safety Board Highway Accident Report: Collapse of I-35W Highway Bridge, Minneapolis, Minnesota, on August 1, 2007
About 6:05 p.m. central daylight time on Wednesday, August 1, 2007, the eight-lane, 1,907-foot long I-35W highway bridge over the Mississippi River in Minneapolis, Minnesota, experienced a catastrophic failure in the main span of the deck truss. As a result, 1,000 feet of the deck truss collapsed, with about 456 feet of the main span falling 108 feet into the 15-foot deep river. A total of 111 vehicles were on the portion of the bridge that collapsed. Of these, 17 were recovered from the water. As a result of the bridge collapse, 13 people died, and 145 people were injured. On the day of the collapse, roadway work was underway on the I-35W bridge, and four of the eight travel lanes (two outside lanes northbound and two inside lanes southbound) were closed to traffic. In the early afternoon, construction equipment and construction aggregates (sand and gravel for making concrete) were delivered and positioned in the two closed inside southbound lanes. The equipment and aggregates, which were being staged for a concrete pour of the southbound lanes that was to begin about 7:00 p.m., were positioned toward the south end of the center section of the deck truss portion of the bridge and were in place by about 2:30 p.m. About 6:05 p.m., a motion-activated surveillance video camera at the Lower St. Anthony Falls Lock and Dam, just west of the I-35W bridge, recorded a portion of the collapse sequence. The video showed the bridge center span separating from the rest of the bridge and falling into the river. Major safety issues identified in this investigation include insufficient bridge design firm quality control procedures for designing bridges, and insufficient Federal and State procedures for reviewing and approving bridge design plans and calculations; lack of guidance for bridge owners with regard to the placement of construction loads on bridges during repair or maintenance activities; exclusion of gusset plates in bridge load rating guidance; lack of inspection guidance for conditions of gusset plate distortion; and inadequate use of technologies for accurately assessing the condition of gusset plates on deck truss bridges. As a result of this accident investigation, the Safety Board makes recommendations to the Federal Highway Administration (FHWA) and the American Association of State Highway and Transportation Officials. One safety recommendation resulting from this investigation was issued to the FHWA in January 2008.
National Transportation Safety Board Highway Accident Report: Collapse of I-35W Highway Bridge, Minneapolis, Minnesota, on August 1, 2007
2008
178 pages
Report
Keine Angabe
Englisch
Transportation Safety , Highway Engineering , Transportation & Traffic Planning , Transportation , Highway bridges , Collapse , Accident investigations , Minnesota , Emergency response , Mississippi River , Deck trusses , Fatalities , Gusset plates , I-35 Highway bridge , Minneapolis(Minnesota) , NTSB/HAR-08/03
Transportation Accident Briefs: Highway
NTIS | 1984
Transportation Accident Briefs: Highway
NTIS | 1984
Minneapolis belt line highway development
Engineering Index Backfile | 1940
Fatal collapse of a highway bridge