It was midnight, Feb. 19, at Cincinnati's Ohio River plant. The Operator shut down one of two operating pumps and the Ohio River filled the entire Station. The water Utility had four days to get its flooded plant working again. Here is a running commentary on an event that wasn't supposed to happen—but did because of poor design, poor Communications, and criminatly improper workmanship.
It was midnight, Feb. 19, at Cincinnati's Ohio River plant. The Operator shut down one of two operating pumps and the Ohio River filled the entire Station. The water Utility had four days to get its flooded plant working again. Here is a running commentary on an event that wasn't supposed to happen—but did because of poor design, poor Communications, and criminatly improper workmanship.
Cincinnati Intake Failure
Bolton, Charles M. (Autor:in)
Journal ‐ American Water Works Association ; 68 ; 627-630
01.12.1976
4 pages
Aufsatz (Zeitschrift)
Elektronische Ressource
Englisch
DELIRIOUS CINCINNATI Zaha Hadid shakes up downtown Cincinnati
British Library Online Contents | 2003
|DELIRIOUS CINCINNATI - Zaha Hadid shakes up downtown Cincinnati.
Online Contents | 2003
|British Library Online Contents | 1999
Engineering Index Backfile | 1933