A platform for research: civil engineering, architecture and urbanism
Lessons Learned from Failure of a Large Diameter Water Pipeline
Construction was near completion for a 28 mile long by 48 inch diameter pipeline when problems were discovered in the hydrostatic testing phase. Sections of pipeline would not hold test pressure and subsequent inspections revealed some pipe segments (joints) of the pipeline had collapsed. Additional internal inspections revealed much of the pipeline had excessive vertical deflection and failure of the mortar lining. The authors were hired to provide forensic engineering, pipeline remediation design, construction observation of the pipeline remediation, and construction contract administration. Forensic engineering revealed the primary cause of failure was inadequate compaction of the pipeline embedment material. Approximately 15 miles of the pipeline were completely removed and replaced with new pipe and 13 miles of pipeline were repaired. The pipeline remediation construction cost was approximately $20 million. Many other problems were discovered during the remediation construction and are discussed in the paper. This paper describes the highlights and lessons learned during the forensic engineering phase and pipeline remediation construction phase.
Lessons Learned from Failure of a Large Diameter Water Pipeline
Construction was near completion for a 28 mile long by 48 inch diameter pipeline when problems were discovered in the hydrostatic testing phase. Sections of pipeline would not hold test pressure and subsequent inspections revealed some pipe segments (joints) of the pipeline had collapsed. Additional internal inspections revealed much of the pipeline had excessive vertical deflection and failure of the mortar lining. The authors were hired to provide forensic engineering, pipeline remediation design, construction observation of the pipeline remediation, and construction contract administration. Forensic engineering revealed the primary cause of failure was inadequate compaction of the pipeline embedment material. Approximately 15 miles of the pipeline were completely removed and replaced with new pipe and 13 miles of pipeline were repaired. The pipeline remediation construction cost was approximately $20 million. Many other problems were discovered during the remediation construction and are discussed in the paper. This paper describes the highlights and lessons learned during the forensic engineering phase and pipeline remediation construction phase.
Lessons Learned from Failure of a Large Diameter Water Pipeline
Gibson, Russell (author) / Allen, Robert (author) / Wilson, Steve (author) / Brunzell, Wayne (author)
International Pipelines Conference 2008 ; 2008 ; Atlanta, Georgia, United States
Pipelines 2008 ; 1-12
2008-07-17
Conference paper
Electronic Resource
English
Failures , Infrastructure , Water pipelines , Pipelines , Costs , Assets
Lessons Learned from Large-Diameter Pipe Failure Case Studies
TIBKAT | 2017
|Some Lessons Learned from Failure of a Pipeline
British Library Conference Proceedings | 2006
|Lessons Learned from Pomerado Pipeline 4 Rehabilitation
ASCE | 2008
|