A platform for research: civil engineering, architecture and urbanism
Taxiway Embankment Construction on Soft Ground Using In Situ Instrumentation and Staged Construction
The Piedmont Triad International Airport (PTIA), Greensboro, NC is undergoing an expansion as a result of the construction of a regional hub for Federal Express. Part of the construction includes an embankment over an alluvial floodplain in a wetlands area. A hybrid ground modification technique was used to stabilize the soft ground, consisting of geogrids, wick drains and rock toe berms. An instrumentation program was implemented to evaluate the changing properties of the alluvial soils, lateral displacements of the embankment foundation soils, settlement of the embankment, determine the fill placement rates or appropriate waiting periods, and to prevent slope failures from occurring. This paper highlights key features of the design and instrumentation system. It describes the project conditions and considerations, the instrumentation system that was installed, the results obtained during construction, and practical issues that were addressed during construction.
Taxiway Embankment Construction on Soft Ground Using In Situ Instrumentation and Staged Construction
The Piedmont Triad International Airport (PTIA), Greensboro, NC is undergoing an expansion as a result of the construction of a regional hub for Federal Express. Part of the construction includes an embankment over an alluvial floodplain in a wetlands area. A hybrid ground modification technique was used to stabilize the soft ground, consisting of geogrids, wick drains and rock toe berms. An instrumentation program was implemented to evaluate the changing properties of the alluvial soils, lateral displacements of the embankment foundation soils, settlement of the embankment, determine the fill placement rates or appropriate waiting periods, and to prevent slope failures from occurring. This paper highlights key features of the design and instrumentation system. It describes the project conditions and considerations, the instrumentation system that was installed, the results obtained during construction, and practical issues that were addressed during construction.
Taxiway Embankment Construction on Soft Ground Using In Situ Instrumentation and Staged Construction
Barrett, Xavier C. (author) / Wells, Thomas R. (author) / Wells, Richard C. (author)
International Foundation Congress and Equipment Expo 2009 ; 2009 ; Orlando, Florida, United States
2009-03-10
Conference paper
Electronic Resource
English
Taxiway Embankment Construction on Soft Ground Using In Situ Instrumentation and Staged Construction
British Library Conference Proceedings | 2009
|Taxiway embankment over soft ground using staged construction
British Library Conference Proceedings | 2009
|Soil Improvement and Staged Embankment Construction in Soft Clays
British Library Conference Proceedings | 2000
|Monitoring the staged construction of a submerged embankment on soft soil
British Library Conference Proceedings | 2007
|