Determining the Probability of Project Cost Overruns
The statistical characteristics of cost overruns experienced from contract award in 276 Australian construction and engineering projects were analyzed. The skewness and kurtosis values of the cost overruns are computed to determine if the empirical distribution of the data follows a normal distribution. The Kolmogorov-Smirnov, Anderson-Darling, and chi-squared nonparametric tests are used to determine the goodness of fit of the selected probability distributions. A three-parameter Frechet probability function is found to describe the behavior of cost overruns and provide the best overall distribution fit. The Frechet distribution is then used to calculate the probability of a cost overrun being experienced. The statistical characteristics of contract size and cost overruns were also analyzed. The Cauchy (), Wakeby (A$1 to 10 million, ) and four-parameter Burr (A$11 to 50 million) tests were found to provide the best distribution fits and used to calculate cost overrun probabilities by contract size. Ascertaining the best fit probability distribution from an empirical distribution at contract award can produce realistic probabilities of cost overruns, which should then be incorporated into a construction cost contingency.
Determining the Probability of Project Cost Overruns
The statistical characteristics of cost overruns experienced from contract award in 276 Australian construction and engineering projects were analyzed. The skewness and kurtosis values of the cost overruns are computed to determine if the empirical distribution of the data follows a normal distribution. The Kolmogorov-Smirnov, Anderson-Darling, and chi-squared nonparametric tests are used to determine the goodness of fit of the selected probability distributions. A three-parameter Frechet probability function is found to describe the behavior of cost overruns and provide the best overall distribution fit. The Frechet distribution is then used to calculate the probability of a cost overrun being experienced. The statistical characteristics of contract size and cost overruns were also analyzed. The Cauchy (), Wakeby (A$1 to 10 million, ) and four-parameter Burr (A$11 to 50 million) tests were found to provide the best distribution fits and used to calculate cost overrun probabilities by contract size. Ascertaining the best fit probability distribution from an empirical distribution at contract award can produce realistic probabilities of cost overruns, which should then be incorporated into a construction cost contingency.
Determining the Probability of Project Cost Overruns
Love, Peter E. D. (author) / Wang, Xiangyu (author) / Sing, Chun-pong (author) / Tiong, Robert L. K. (author)
Journal of Construction Engineering and Management ; 139 ; 321-330
2012-04-28
102013-01-01 pages
Article (Journal)
Electronic Resource
English
Determining the Probability of Project Cost Overruns
British Library Online Contents | 2013
|Determining the Probability of Project Cost Overruns
Online Contents | 2013
|Project cost overruns and risk management
British Library Conference Proceedings | 2002
|British Library Online Contents | 1996
|Review of construction journals on causes of project cost overruns
Emerald Group Publishing | 2020
|