Common risks affecting time overrun in road construction projects in Palestine: Contractors’ perspective
The construction sector is one of the key economic sectors and is the main force motivating the Palestinian national economy. However, it suffers from number of problems that affect time, cost and quality performances. This study aims at identifying the common risks affecting time overrun in road construction projects in the West Bank in Palestine from contractors’ viewpoint. 45 factors that might cause delays of road construction projects were defined through a detailed literature review. A questionnaire survey was performed to rank the considered factors in terms of severity and frequency. The analysis of the survey indicated that the top risks affecting time overrun in road construction projects in Palestine are: financial status of the contractors, payments delay by the owner, political situation, segmentation of the West Bank, poor communication between construction parties, lack of equipment efficiency, and high competition in bids.
Common risks affecting time overrun in road construction projects in Palestine: Contractors’ perspective
The construction sector is one of the key economic sectors and is the main force motivating the Palestinian national economy. However, it suffers from number of problems that affect time, cost and quality performances. This study aims at identifying the common risks affecting time overrun in road construction projects in the West Bank in Palestine from contractors’ viewpoint. 45 factors that might cause delays of road construction projects were defined through a detailed literature review. A questionnaire survey was performed to rank the considered factors in terms of severity and frequency. The analysis of the survey indicated that the top risks affecting time overrun in road construction projects in Palestine are: financial status of the contractors, payments delay by the owner, political situation, segmentation of the West Bank, poor communication between construction parties, lack of equipment efficiency, and high competition in bids.
Common risks affecting time overrun in road construction projects in Palestine: Contractors’ perspective
Mahamid, Ibrahim (author)
2013-06-18
doi:10.5130/AJCEB.v13i2.3194
Construction Economics and Building; Vol 13 No 2 (2013): AJCEB; 45-53 ; 2204-9029
Article (Journal)
Electronic Resource
English
DDC:
690
DOAJ | 2013
|DOAJ | 2013
|Practical behaviour of managing time-overrun risks in construction projects
British Library Conference Proceedings | 1996
|Risks affecting the performance of Ethiopian domestic road construction contractors
Taylor & Francis Verlag | 2023
|Key risks in construction projects in Italy: contractors' perspective
Online Contents | 2017
|