Time-Cost Relationship for Predicting Construction Duration
The paper aims at creating a model of road construction duration in the function of project qualities including the construction cost. The qualities considered are likely to be defined or possible to be estimated at early stages of project planning, giving no consideration to construction method or organisation of works. Potentially, the model might be applied by construction clients in their feasibility studies. It could also be used for comparing construction duration or construction rate with respect to project qualities.
Time-Cost Relationship for Predicting Construction Duration
The paper aims at creating a model of road construction duration in the function of project qualities including the construction cost. The qualities considered are likely to be defined or possible to be estimated at early stages of project planning, giving no consideration to construction method or organisation of works. Potentially, the model might be applied by construction clients in their feasibility studies. It could also be used for comparing construction duration or construction rate with respect to project qualities.
Time-Cost Relationship for Predicting Construction Duration
Agata Czarnigowska (author) / Anna Sobotka (author)
2013
Article (Journal)
Electronic Resource
Unknown
Metadata by DOAJ is licensed under CC BY-SA 1.0
Time-cost relationship for predicting construction duration
Springer Verlag | 2013
|Time-cost relationship for predicting construction duration
British Library Online Contents | 2013
|Predicting Contract Duration for Building Construction: Is Bromilow’s Time-Cost Model a Panacea?
Online Contents | 2016
|A neurofuzzy model for predicting the cost and duration of construction projects
British Library Conference Proceedings | 1998
|