Research and Analysis on the Influence of Small Clear Distance Drilling and Blasting Method on the Existing Tunnel Structure
In order to study the vibration influence of tunnel drilling and blasting method on the built tunnel with small clear distance, taking the intersection of Zhuhai Dahengqinshan No. 1 tunnel and Zhuji urban rail tunnel as the engineering background, we used ABAQUS finite element software to conduct numerical simulation analysis on the influence of different blasting loads on existing tunnels with small clear distance in Zhuji tunnel construction. The following conclusions were drawn: the blasting construction of the tunnel under construction had the greatest impact on the vault of the existing tunnel; when the peak load was reduced by half, the stress value, vertical displacement, and resultant velocity of Mises were also reduced by half, which indicates that reducing the peak value of blasting load appropriately can ensure the safety of tunnel construction. When the peak load is 2.7 MPa, the measured and simulated values were less than the resultant velocity limit required by the specification. In addition, the relative error between the measured value and the simulated value was less than 5%, indicating the accuracy of the numerical simulation.
Research and Analysis on the Influence of Small Clear Distance Drilling and Blasting Method on the Existing Tunnel Structure
In order to study the vibration influence of tunnel drilling and blasting method on the built tunnel with small clear distance, taking the intersection of Zhuhai Dahengqinshan No. 1 tunnel and Zhuji urban rail tunnel as the engineering background, we used ABAQUS finite element software to conduct numerical simulation analysis on the influence of different blasting loads on existing tunnels with small clear distance in Zhuji tunnel construction. The following conclusions were drawn: the blasting construction of the tunnel under construction had the greatest impact on the vault of the existing tunnel; when the peak load was reduced by half, the stress value, vertical displacement, and resultant velocity of Mises were also reduced by half, which indicates that reducing the peak value of blasting load appropriately can ensure the safety of tunnel construction. When the peak load is 2.7 MPa, the measured and simulated values were less than the resultant velocity limit required by the specification. In addition, the relative error between the measured value and the simulated value was less than 5%, indicating the accuracy of the numerical simulation.
Research and Analysis on the Influence of Small Clear Distance Drilling and Blasting Method on the Existing Tunnel Structure
Haibin Huang (author) / Peng Li (author) / Chuang Wang (author) / Bingxiang Yuan (author) / Minjie Chen (author) / Weimin Feng (author)
2021
Article (Journal)
Electronic Resource
Unknown
Metadata by DOAJ is licensed under CC BY-SA 1.0
Influence of Small, Clear Distance Cross-Tunnel Blasting Excavation on Existing Tunnel below