A platform for research: civil engineering, architecture and urbanism
Grout bedding speeds pipe laying
It is shown how utilization of cement-sand-water slurry instead of compacted backfill made it possible to cut 5 mo from 13-mo pipe job in construction of 49-mi network of irrigation lines; grout is discharged in two passes; after grout has hardened around pipe, rest of trench can be filled with dirt without need of compaction. (09661)
Grout bedding speeds pipe laying
It is shown how utilization of cement-sand-water slurry instead of compacted backfill made it possible to cut 5 mo from 13-mo pipe job in construction of 49-mi network of irrigation lines; grout is discharged in two passes; after grout has hardened around pipe, rest of trench can be filled with dirt without need of compaction. (09661)
Grout bedding speeds pipe laying
West Constr
Western Construction ; 43
1968
Article (Journal)
English
© Metadata Copyright Elsevier B. V. All rights reserved.
Efficient trench bracing speeds pipe laying
Engineering Index Backfile | 1957
PU HYBRID AS BEDDING MORTAR, ADHESIVE, JOINT GROUT OR JOINT FILLER
European Patent Office | 2018
|Transparent pipe bedding - Recording the bedding condition of concrete pipes
British Library Online Contents | 2007
|Transparent pipe bedding - Recording the bedding condition of concrete pipes
British Library Conference Proceedings | 2007
|