Hybrid fuzzy arithmetic-based model for determining contingency reserve
Abstract Calculating an accurate contingency reserve amount is vital to managing construction project costs and risks. Current methods for determining contingency have limitations in incorporating risk response actions (RRAs), accounting for insufficient quantitative historical data, considering time-dependent variables, and capturing cause-and-effect interactions between risk events (REs) together and with RRAs. This paper presents a hybrid fuzzy arithmetic-based contingency reserve model (HFACRM) that addresses these limitations by 1) considering time-dependent probability and impact values of risk events and RRAs, 2) modeling causal relationships among variables affecting contingency, and 3) addressing subjective uncertainty of linguistic evaluations in risk management. HFACRM considers more realistic complexities and characteristics of projects compared to other models, resulting in a significant improvement in the accuracy and effectiveness of determining contingency reserve. A wind farm power generation project was used as a case study to demonstrate and validate HFACRM.
Highlights A hybrid fuzzy method is proposed to determine contingency reserve. The time-dependent nature of risks and their causal relationships are considered. Linguistic evaluations are used to solve problem of reliance on quantitative data. Effect, interaction, and implementing cost of risk response actions are considered. The results are more accurate compared with Monte Carlo Simulation software.
Hybrid fuzzy arithmetic-based model for determining contingency reserve
Abstract Calculating an accurate contingency reserve amount is vital to managing construction project costs and risks. Current methods for determining contingency have limitations in incorporating risk response actions (RRAs), accounting for insufficient quantitative historical data, considering time-dependent variables, and capturing cause-and-effect interactions between risk events (REs) together and with RRAs. This paper presents a hybrid fuzzy arithmetic-based contingency reserve model (HFACRM) that addresses these limitations by 1) considering time-dependent probability and impact values of risk events and RRAs, 2) modeling causal relationships among variables affecting contingency, and 3) addressing subjective uncertainty of linguistic evaluations in risk management. HFACRM considers more realistic complexities and characteristics of projects compared to other models, resulting in a significant improvement in the accuracy and effectiveness of determining contingency reserve. A wind farm power generation project was used as a case study to demonstrate and validate HFACRM.
Highlights A hybrid fuzzy method is proposed to determine contingency reserve. The time-dependent nature of risks and their causal relationships are considered. Linguistic evaluations are used to solve problem of reliance on quantitative data. Effect, interaction, and implementing cost of risk response actions are considered. The results are more accurate compared with Monte Carlo Simulation software.
Hybrid fuzzy arithmetic-based model for determining contingency reserve
Fateminia, Seyed Hamed (author) / Fayek, Aminah Robinson (author)
2023-03-30
Article (Journal)
Electronic Resource
English
Fuzzy Arithmetic Risk Analysis Approach to Determine Construction Project Contingency
Online Contents | 2016
|Fuzzy Arithmetic Risk Analysis Approach to Determine Construction Project Contingency
Online Contents | 2016
|A Fuzzy Number Interval Arithmetic based Fuzzy MCDM Algorithm
British Library Online Contents | 2002
|Determining Reserve and Equalizing Storages
Wiley | 1962
|