Time-cost optimization in repetitive project scheduling with limited resources
The purpose of this research is to develop a time-cost optimization model to schedule repetitive projects while considering limited resource availability.
The model is based on the constraint programming (CP) framework; it integrates multiple scheduling characteristics of repetitive activities such as continuous or fragmented execution, atypical activities and coexistence of different modes in an activity. To improve project performance while avoiding inefficient hiring and firing conditions, the strategy of bidirectional acceleration is presented and implemented, which requires keeping regular changes in the execution modes between successive subactivities in the same activity.
Two case studies involving a real residential building construction project and a hotel refurbishing project are used to demonstrate the application of the proposed model based on four different scenarios. The results show that (1) the CP model has great advantages in terms of solving speed and solution quality than its equivalent mathematical model, (2) higher project performance can be obtained compared to using previously developed models and (3) the model can be easily replicated or even modified to enable multicrew implementation.
The original contribution of this research is presenting a novel CP-based repetitive scheduling optimization model to solve the multimode resource-constrained time-cost tradeoff problem of repetitive projects. The model has the capability of minimizing the project total cost that is composed of direct costs, indirect costs, early completion incentives and late completion penalties.
Time-cost optimization in repetitive project scheduling with limited resources
The purpose of this research is to develop a time-cost optimization model to schedule repetitive projects while considering limited resource availability.
The model is based on the constraint programming (CP) framework; it integrates multiple scheduling characteristics of repetitive activities such as continuous or fragmented execution, atypical activities and coexistence of different modes in an activity. To improve project performance while avoiding inefficient hiring and firing conditions, the strategy of bidirectional acceleration is presented and implemented, which requires keeping regular changes in the execution modes between successive subactivities in the same activity.
Two case studies involving a real residential building construction project and a hotel refurbishing project are used to demonstrate the application of the proposed model based on four different scenarios. The results show that (1) the CP model has great advantages in terms of solving speed and solution quality than its equivalent mathematical model, (2) higher project performance can be obtained compared to using previously developed models and (3) the model can be easily replicated or even modified to enable multicrew implementation.
The original contribution of this research is presenting a novel CP-based repetitive scheduling optimization model to solve the multimode resource-constrained time-cost tradeoff problem of repetitive projects. The model has the capability of minimizing the project total cost that is composed of direct costs, indirect costs, early completion incentives and late completion penalties.
Time-cost optimization in repetitive project scheduling with limited resources
Time-cost optimization with limited resources
Zou, Xin (author) / Zhang, Lihui (author) / Zhang, Qian (author)
Engineering, Construction and Architectural Management ; 29 ; 669-701
2021-03-16
33 pages
Article (Journal)
Electronic Resource
English
Scenario‐oriented repetitive project scheduling optimization
Wiley | 2023
|Scheduling of Repetitive Projects with Cost Optimization
British Library Online Contents | 1993
|Scheduling of Repetitive Projects with Cost Optimization
Online Contents | 1993
|Taylor & Francis Verlag | 2023
|