Information commissioning: bridging the gap between digital and physical built assets
As the use of building information modeling (BIM) for facilities management (FM) continues to grow, questions remain around the quality and completeness of digital assets to support FM practices. This paper aims to examine the current gap between digital and physical assets in the absence of formal information requirements and its impact on the handover process.
An action-research was carried out with a large public organization to understand the challenges of their current FM processes and the steps required in developing an asset information model (AIM) from a project information model (PIM). A mixed method approach was employed with interviews, document analysis and an exploratory pilot case study.
This paper investigates the process, the challenges and the level of effort of the information commissioning process to create a fit-for-use AIM. Four distinct steps were identified in the process as follows: analyzing the handover PIM and documents, extracting FM-specific information, populating the model with the information and attaching operations and maintenance (O&M) documents. The research highlights the significant amount of effort that is required when no specific asset information requirements are formulated at the project onset.
The paper presents an information commissioning process that helps to develop an AIM from a PIM. Understanding the impact of the lack of requirements on the information commissioning process can help asset owners understand the importance of defining and articulating their information requirements up front.
This paper provides empirical evidence of the impact of the absence of formal information requirements on the development of a fit-for-use AIM.
Information commissioning: bridging the gap between digital and physical built assets
As the use of building information modeling (BIM) for facilities management (FM) continues to grow, questions remain around the quality and completeness of digital assets to support FM practices. This paper aims to examine the current gap between digital and physical assets in the absence of formal information requirements and its impact on the handover process.
An action-research was carried out with a large public organization to understand the challenges of their current FM processes and the steps required in developing an asset information model (AIM) from a project information model (PIM). A mixed method approach was employed with interviews, document analysis and an exploratory pilot case study.
This paper investigates the process, the challenges and the level of effort of the information commissioning process to create a fit-for-use AIM. Four distinct steps were identified in the process as follows: analyzing the handover PIM and documents, extracting FM-specific information, populating the model with the information and attaching operations and maintenance (O&M) documents. The research highlights the significant amount of effort that is required when no specific asset information requirements are formulated at the project onset.
The paper presents an information commissioning process that helps to develop an AIM from a PIM. Understanding the impact of the lack of requirements on the information commissioning process can help asset owners understand the importance of defining and articulating their information requirements up front.
This paper provides empirical evidence of the impact of the absence of formal information requirements on the development of a fit-for-use AIM.
Information commissioning: bridging the gap between digital and physical built assets
Kim, Soojung (author) / Poirier, Erik A. (author) / Staub-French, Sheryl (author)
Journal of Facilities Management ; 18 ; 231-245
2020-07-06
1 pages
Article (Journal)
Electronic Resource
English
Witness Testing for Large Equipment Assets before Commissioning
TIBKAT | 2021
|Building information modelling to support maintenance management of healthcare built assets
Emerald Group Publishing | 2019
|