Design and construction risks in BOT type mega transportation projects
In build-operate-transfer (BOT) transportation projects, design and construction phases are critical in terms of their effect on time and cost overruns. The purpose of this paper is to identify the role of risk factors affecting these phases and their significance level for BOT transportation projects.
Design and construction risks were determined and then validated by focus group discussions. Afterwards, an illustrated case study was presented to better understand the effects of determined risks in a BOT mega transportation project. As the last step of the study, the fuzzy analytical hierarchy process method was used to prioritize risk factors.
The prominent risk factors were found out as occupational accidents, integration between design and construction phases and excessive design variations.
Different kinds of BOT transportation projects in different countries might be executed very differently considering specific social, political, economic and other factors. However, the results of the study are important in terms of the specific lessons learned from the case study that can be used as a foundation for developing possible risk mitigation measures.
Though the risk management of BOT projects has been investigated frequently in the literature, there is a knowledge gap in the quantitative evaluation of risk significance specific to design and construction risks. The prioritization of determined risks with an associated case from a mega transportation project will contribute to the BOT project practitioners about possible challenges in design and construction phases in BOT mega transportation projects.
Design and construction risks in BOT type mega transportation projects
In build-operate-transfer (BOT) transportation projects, design and construction phases are critical in terms of their effect on time and cost overruns. The purpose of this paper is to identify the role of risk factors affecting these phases and their significance level for BOT transportation projects.
Design and construction risks were determined and then validated by focus group discussions. Afterwards, an illustrated case study was presented to better understand the effects of determined risks in a BOT mega transportation project. As the last step of the study, the fuzzy analytical hierarchy process method was used to prioritize risk factors.
The prominent risk factors were found out as occupational accidents, integration between design and construction phases and excessive design variations.
Different kinds of BOT transportation projects in different countries might be executed very differently considering specific social, political, economic and other factors. However, the results of the study are important in terms of the specific lessons learned from the case study that can be used as a foundation for developing possible risk mitigation measures.
Though the risk management of BOT projects has been investigated frequently in the literature, there is a knowledge gap in the quantitative evaluation of risk significance specific to design and construction risks. The prioritization of determined risks with an associated case from a mega transportation project will contribute to the BOT project practitioners about possible challenges in design and construction phases in BOT mega transportation projects.
Design and construction risks in BOT type mega transportation projects
Design and construction risks
Aladağ, Hande (author) / Işık, Zeynep (author)
Engineering, Construction and Architectural Management ; 26 ; 2223-2242
2019-06-19
20 pages
Article (Journal)
Electronic Resource
English
Asphalt technology for mega transportation projects
British Library Conference Proceedings | 2000
|ASPHALT TECHNOLOGY FOR MEGA TRANSPORTATION PROJECTS
British Library Conference Proceedings | 1999
|Risks assessment using structural equation modeling: mega housing projects construction in Egypt
Taylor & Francis Verlag | 2023
|A Hybrid Approach for Dynamic Simulation of Safety Risks in Mega Construction Projects
DOAJ | 2020
|A Hybrid Approach for Dynamic Simulation of Safety Risks in Mega Construction Projects
BASE | 2020
|