Commercial reviews in the tender process of contractors
–
The purpose of this paper is to show the extent to which clients amend standard form contracts in practice, the locus of the amendments, and how contractors respond to the amendments when putting together a bid.
Four live observational case studies were carried out in two of the top 20 UK construction firms. The whole process used to review the proposed terms and conditions of the contract was shadowed using participant observation, interview and documentary analysis.
All four cases showed strong evidence of amendments relating mostly to payment and contractual aspects: 83 amendments in Case Study 1 (CS1), 80 in CS2, 15 in CS3 and 29 in CS4. This comprised clauses that were modified (37 per cent), substituted (23 per cent), deleted (7 per cent) and new additions (33 per cent). Risks inherent in the amendments were mostly addressed through contractual rather than price mechanisms, to reflect commercial imperatives. “Qualifications” and “clarifications” were included in the tender submissions for post-tender negotiations. Thus, the amendments did not necessarily influence price. There was no evidence of a “standard-form contract“ being used as such, although clients may draw on published “standard-form contracts” to derive the forms of contract actually used in practice.
Contractors should pay attention to clauses relating to contractual and financial aspects when reviewing tender documents. Clients should draft equitable payment and contractual terms and conditions to reduce risk of dispute. Indeed, it is prudent for clients not to pass on inestimable risks.
A better understanding of the extent and locus of amendments in standard form contracts, and how contractors respond, is provided.
Commercial reviews in the tender process of contractors
–
The purpose of this paper is to show the extent to which clients amend standard form contracts in practice, the locus of the amendments, and how contractors respond to the amendments when putting together a bid.
Four live observational case studies were carried out in two of the top 20 UK construction firms. The whole process used to review the proposed terms and conditions of the contract was shadowed using participant observation, interview and documentary analysis.
All four cases showed strong evidence of amendments relating mostly to payment and contractual aspects: 83 amendments in Case Study 1 (CS1), 80 in CS2, 15 in CS3 and 29 in CS4. This comprised clauses that were modified (37 per cent), substituted (23 per cent), deleted (7 per cent) and new additions (33 per cent). Risks inherent in the amendments were mostly addressed through contractual rather than price mechanisms, to reflect commercial imperatives. “Qualifications” and “clarifications” were included in the tender submissions for post-tender negotiations. Thus, the amendments did not necessarily influence price. There was no evidence of a “standard-form contract“ being used as such, although clients may draw on published “standard-form contracts” to derive the forms of contract actually used in practice.
Contractors should pay attention to clauses relating to contractual and financial aspects when reviewing tender documents. Clients should draft equitable payment and contractual terms and conditions to reduce risk of dispute. Indeed, it is prudent for clients not to pass on inestimable risks.
A better understanding of the extent and locus of amendments in standard form contracts, and how contractors respond, is provided.
Commercial reviews in the tender process of contractors
Laryea, Samuel (author) / Hughes, Will (author)
Engineering, Construction and Architectural Management ; 16 ; 558-572
2009-11-06
15 pages
Article (Journal)
Electronic Resource
English
Commercial reviews in the tender process of contractors
Online Contents | 2009
|Subcontract and supply enquiries in the tender process of contractors
British Library Online Contents | 2009
|Subcontract and supply enquiries in the tender process of contractors
Online Contents | 2009
|Tender wars - How contractors recoup the cost of tendering.
Online Contents | 2001