Integrated project delivery implementation framework for water and wastewater treatment plant projects
The public nature of water and wastewater construction capital projects has rendered design-bid-build (DBB) as the delivery method of choice for such projects over the past years. Shortcomings inherent to DBB have had a negative effect on the key performance indicators (KPIs) of these projects. Numerous studies have been published about the benefits offered by integrated project delivery (IPD) in improving the delivery of DBB projects. Links correlating IPD principles to improvements in KPIs of DBB construction projects have not been established scientifically, thus leaving owners with no guidance on which IPD principle(s) to implement in order to improve a particular project KPI. The paper aims to discuss this issue.
Actual data were collected from 43 water and wastewater construction projects – including two control projects with full implementation of selective IPD principles – and used to compute major projects KPIs. Regression analysis and a focus group are then utilized to determine the effect of each implemented IPD principle on various project KPIs.
Implementation of open communication was found to have a significant effect on reducing project cost overrun, and the co-location of teams significantly reduced the time to respond to RFIs. Collaborative decision making significantly reduced the cost of field rework. Other IPD principles showed less-significant effects on project KPIs and were concluded to be ineffective at improving the projects’ performance.
An implementation framework is developed that can guide utility owners on which IPD principle(s) to implement in order to improve specific project KPIs.
This study demonstrates that not all IPD principles will result in performance improvement of a project. A selective and cost-effective implementation of certain IPD principle will have to be based on the nature of the project and the particular KPIs targeted for improvement.
Integrated project delivery implementation framework for water and wastewater treatment plant projects
The public nature of water and wastewater construction capital projects has rendered design-bid-build (DBB) as the delivery method of choice for such projects over the past years. Shortcomings inherent to DBB have had a negative effect on the key performance indicators (KPIs) of these projects. Numerous studies have been published about the benefits offered by integrated project delivery (IPD) in improving the delivery of DBB projects. Links correlating IPD principles to improvements in KPIs of DBB construction projects have not been established scientifically, thus leaving owners with no guidance on which IPD principle(s) to implement in order to improve a particular project KPI. The paper aims to discuss this issue.
Actual data were collected from 43 water and wastewater construction projects – including two control projects with full implementation of selective IPD principles – and used to compute major projects KPIs. Regression analysis and a focus group are then utilized to determine the effect of each implemented IPD principle on various project KPIs.
Implementation of open communication was found to have a significant effect on reducing project cost overrun, and the co-location of teams significantly reduced the time to respond to RFIs. Collaborative decision making significantly reduced the cost of field rework. Other IPD principles showed less-significant effects on project KPIs and were concluded to be ineffective at improving the projects’ performance.
An implementation framework is developed that can guide utility owners on which IPD principle(s) to implement in order to improve specific project KPIs.
This study demonstrates that not all IPD principles will result in performance improvement of a project. A selective and cost-effective implementation of certain IPD principle will have to be based on the nature of the project and the particular KPIs targeted for improvement.
Integrated project delivery implementation framework for water and wastewater treatment plant projects
IPD implementation framework
Andary, Elie Georges (author) / Abi Shdid, Caesar (author) / Chowdhury, Arindam (author) / Ahmad, Irtishad (author)
Engineering, Construction and Architectural Management ; 27 ; 609-633
2019-11-07
25 pages
Article (Journal)
Electronic Resource
English
Integrated Project Delivery for Infrastructure Projects in Peru
TIBKAT | 2018
|Alternative Project Delivery Methods for Water and Wastewater Projects: Do They Save Time and Money?
Online Contents | 2011
|