Construction duration of residential building projects in Germany
–
Planning the construction duration is an important consideration in any construction project. Indicators that permit an early forecast of the duration provide the basis for such planning. To date, such a basis has been lacking in the German-speaking area. This paper aims to discuss this matter.
Indicators are identified that enable a forecast of the construction duration. In addition, a simple regression model is provided to assist in selecting construction speed indicators. This empirical analysis relies on the data, collected on a uniform basis, from 115 German residential buildings.
Project size (measured in m2 gross external floor area) and project standard (measured in € building construction cost/m2 gross external floor area) are found to be significant drivers of construction speed. It appears that project size, in contrast to the project standard, is positively correlated with construction speed.
An expansion of the data pool is required for more extensive study. On the one hand, this means including relevant drivers that have only been insufficiently considered to date, such as project complexity, project environment, management-related attributes. On the other hand, the data pool must also be expanded to include other types of use.
Construction duration of residential building projects in Germany
–
Planning the construction duration is an important consideration in any construction project. Indicators that permit an early forecast of the duration provide the basis for such planning. To date, such a basis has been lacking in the German-speaking area. This paper aims to discuss this matter.
Indicators are identified that enable a forecast of the construction duration. In addition, a simple regression model is provided to assist in selecting construction speed indicators. This empirical analysis relies on the data, collected on a uniform basis, from 115 German residential buildings.
Project size (measured in m2 gross external floor area) and project standard (measured in € building construction cost/m2 gross external floor area) are found to be significant drivers of construction speed. It appears that project size, in contrast to the project standard, is positively correlated with construction speed.
An expansion of the data pool is required for more extensive study. On the one hand, this means including relevant drivers that have only been insufficiently considered to date, such as project complexity, project environment, management-related attributes. On the other hand, the data pool must also be expanded to include other types of use.
Construction duration of residential building projects in Germany
Stoy, Christian (author) / Dreier, Frank (author) / Schalcher, Hans-Rudolf (author)
2007-01-16
13 pages
Article (Journal)
Electronic Resource
English
Construction duration of residential building projects in Germany
Online Contents | 2007
|Determinants of construction duration for building projects in Germany
Online Contents | 2012
|Determinants of construction duration for building projects in Germany
Emerald Group Publishing | 2012
|Construction Claims in Residential Building Projects in Saudi Arabia
Online Contents | 1996
|Analysis of Factors Causing Cost Overruns in Residential Building Construction Projects
BASE | 2020
|