Evaluating and selecting the supplier in prefabricated megaprojects using extended fuzzy TOPSIS under hesitant environment: a case study from China
Prefabricated components sustainable supplier (PCSS) selection is critical to the success of prefabricated projects. However, limited studies have addressed the uncertainty and complexities during the selection process, particularly in multi-criterion group decision-making (MCGDM) circumstances. Hence, the research aims to develop a group decision-making model using a modified fuzzy MCGDM approach for PCSS selection under uncertain situation.
The proposed study develops a framework for sorting decisions in PCSS selection by using the hesitant fuzzy technique for order preference by similarity to ideal solution (HF-TOPSIS) method. The maximum consistency (MC) model is used to calculate the weights of decision makers (DMs) based on the cardinality and sequence of decision data.
The proposed framework has been successfully applied and illustrated in the case example of CB01 contract section in Hong Kong-Zhuhai-Macao Bridge (HZMB) megaproject. The results show various complicated decision-making scenarios can be addressed through the proposed approach. The MC model is able to calculate the weights of DMs based on the cardinality and sequence of decision data.
The research contributes to improving accuracy and reliability decision-making processes for PCSS selection, especially under hesitant and fuzzy situations in prefabricated megaprojects.
Evaluating and selecting the supplier in prefabricated megaprojects using extended fuzzy TOPSIS under hesitant environment: a case study from China
Prefabricated components sustainable supplier (PCSS) selection is critical to the success of prefabricated projects. However, limited studies have addressed the uncertainty and complexities during the selection process, particularly in multi-criterion group decision-making (MCGDM) circumstances. Hence, the research aims to develop a group decision-making model using a modified fuzzy MCGDM approach for PCSS selection under uncertain situation.
The proposed study develops a framework for sorting decisions in PCSS selection by using the hesitant fuzzy technique for order preference by similarity to ideal solution (HF-TOPSIS) method. The maximum consistency (MC) model is used to calculate the weights of decision makers (DMs) based on the cardinality and sequence of decision data.
The proposed framework has been successfully applied and illustrated in the case example of CB01 contract section in Hong Kong-Zhuhai-Macao Bridge (HZMB) megaproject. The results show various complicated decision-making scenarios can be addressed through the proposed approach. The MC model is able to calculate the weights of DMs based on the cardinality and sequence of decision data.
The research contributes to improving accuracy and reliability decision-making processes for PCSS selection, especially under hesitant and fuzzy situations in prefabricated megaprojects.
Evaluating and selecting the supplier in prefabricated megaprojects using extended fuzzy TOPSIS under hesitant environment: a case study from China
PCSS selection under uncertain situation
Liang, Ru (author) / Li, Rui (author) / Yan, Xue (author) / Xue, Zhenzhen (author) / Wei, Xin (author)
Engineering, Construction and Architectural Management ; 30 ; 1902-1931
2023-05-24
30 pages
Article (Journal)
Electronic Resource
English
Taylor & Francis Verlag | 2023
|A hybrid group decision model for green supplier selection: a case study of megaprojects
Emerald Group Publishing | 2019
|Group Decision Making under Multiplicative Hesitant Fuzzy Environment
British Library Online Contents | 2014
|DOAJ | 2018
|