Shallowly-buried soft soil integrated trench reinforcing device and construction method
The invention discloses a shallowly-buried soft soil integrated trench reinforcing device and a construction method. At first, slope excavation is carried out on a foundation pit, drain ditches are formed outside the pit, then geogrids and rubble layers are laid on the pit bottom from bottom to top in a trapezoidal reciprocating layering mode, soil body backfill is carried out, a crushed stone sand layer is laid, a concrete cushion is poured, an integrated trench body, embedded threaded rods and waterstop steel plates are installed, transverse and longitudinal H-shaped steel beams and steel pipe columns are installed in the integrated trench body, cable-stayed angle steel and vertical steel plates are installed on the outer surfaces of the side walls of the integrated trench body, the cable-stayed angle steel is fixed to the embedded threaded rods through connecting steel plates and nuts, second-layer soil body backfill is carried out, geogrids and rubble layers are laid again, and finally third-layer soil body backfill is carried out. According to the construction method, by means of indirect reinforcing of composite laminated structures of the geogrids and the rubble layers and direct reinforcing of the reinforcing members installed inside and outside the trench body, the stability in the integrated trench construction process and during the operation period is greatly improved.
Shallowly-buried soft soil integrated trench reinforcing device and construction method
The invention discloses a shallowly-buried soft soil integrated trench reinforcing device and a construction method. At first, slope excavation is carried out on a foundation pit, drain ditches are formed outside the pit, then geogrids and rubble layers are laid on the pit bottom from bottom to top in a trapezoidal reciprocating layering mode, soil body backfill is carried out, a crushed stone sand layer is laid, a concrete cushion is poured, an integrated trench body, embedded threaded rods and waterstop steel plates are installed, transverse and longitudinal H-shaped steel beams and steel pipe columns are installed in the integrated trench body, cable-stayed angle steel and vertical steel plates are installed on the outer surfaces of the side walls of the integrated trench body, the cable-stayed angle steel is fixed to the embedded threaded rods through connecting steel plates and nuts, second-layer soil body backfill is carried out, geogrids and rubble layers are laid again, and finally third-layer soil body backfill is carried out. According to the construction method, by means of indirect reinforcing of composite laminated structures of the geogrids and the rubble layers and direct reinforcing of the reinforcing members installed inside and outside the trench body, the stability in the integrated trench construction process and during the operation period is greatly improved.
Shallowly-buried soft soil integrated trench reinforcing device and construction method
WANG SHUHONG (author) / CAI ZHI (author) / WANG PENGYU (author) / XING MIN (author) / HUANG LIFU (author)
2015-08-19
Patent
Electronic Resource
English
IPC:
E02D
FOUNDATIONS
,
Gründungen
Upward Pipe—Soil Interaction for Shallowly Buried Pipelines in Dense Sand
British Library Online Contents | 2018
|Natural ventilation of urban shallowly-buried road tunnels with roof openings
British Library Online Contents | 2017
|Construction method of integrated pipe trench in soft soil
European Patent Office | 2015
|