Light steel keel overall synchronous lifting construction method
The embodiment of the invention discloses a light steel keel overall synchronous lifting construction method in the technical field of building construction. The light steel keel overall synchronous lifting construction method includes the following steps that S1, construction preparation is conducted, wherein a construction site, construction machines and necessary materials in the construction process are prepared; S2, light steel keels are welded and spliced on the ground, wherein according to the requirements of a drawing, the main keels and the secondary keels are arranged in order, and each member is labeled with a welding sequence serial number; and S3, a winch unit is installed and debugged. By the adoption of the method, the light steel keels are welded and spliced overall on theground and then lifted overall at one time, the time spent on work high above the ground is shortened, safety risks are reduced, and a construction period is greatly shortened. Lifting engineering achieves an expected effect, the engineering construction quality and safety are guaranteed, and the construction period is greatly shortened as well.
本发明实施例公开了建筑施工技术领域中的一种轻钢龙骨整体同步提升施工方法。本发明的轻钢龙骨整体同步提升施工方法,包括如下步骤:S1、施工准备;准备施工现场和施工机械以及施工时必备的材料;S2、轻钢龙骨地面焊接拼装;根据图纸要求,将主龙骨和次龙骨整齐排列,标注每个构建的焊接顺序编号;S3、卷扬机组的安装与调试。本发明通过轻钢龙骨在地面上进行整体焊接拼装,然后进行一次性整体提升,减少了在高空作业的时间,降低安全风险,并且大大缩短了施工工期。使吊装工程既达到预期效果,又确保了工程施工质量和安全性,也大大加快了工期。
Light steel keel overall synchronous lifting construction method
The embodiment of the invention discloses a light steel keel overall synchronous lifting construction method in the technical field of building construction. The light steel keel overall synchronous lifting construction method includes the following steps that S1, construction preparation is conducted, wherein a construction site, construction machines and necessary materials in the construction process are prepared; S2, light steel keels are welded and spliced on the ground, wherein according to the requirements of a drawing, the main keels and the secondary keels are arranged in order, and each member is labeled with a welding sequence serial number; and S3, a winch unit is installed and debugged. By the adoption of the method, the light steel keels are welded and spliced overall on theground and then lifted overall at one time, the time spent on work high above the ground is shortened, safety risks are reduced, and a construction period is greatly shortened. Lifting engineering achieves an expected effect, the engineering construction quality and safety are guaranteed, and the construction period is greatly shortened as well.
本发明实施例公开了建筑施工技术领域中的一种轻钢龙骨整体同步提升施工方法。本发明的轻钢龙骨整体同步提升施工方法,包括如下步骤:S1、施工准备;准备施工现场和施工机械以及施工时必备的材料;S2、轻钢龙骨地面焊接拼装;根据图纸要求,将主龙骨和次龙骨整齐排列,标注每个构建的焊接顺序编号;S3、卷扬机组的安装与调试。本发明通过轻钢龙骨在地面上进行整体焊接拼装,然后进行一次性整体提升,减少了在高空作业的时间,降低安全风险,并且大大缩短了施工工期。使吊装工程既达到预期效果,又确保了工程施工质量和安全性,也大大加快了工期。
Light steel keel overall synchronous lifting construction method
一种轻钢龙骨整体同步提升施工方法
LI XIANGQUAN (author) / WU GUOBIN (author) / DENG RONGBING (author) / LUO JIANZHONG (author) / LIANG YUZHONG (author)
2020-05-08
Patent
Electronic Resource
Chinese
Light steel keel structure and construction method thereof
European Patent Office | 2021
|