Pipe curtain cover excavation reverse construction method for subway station construction
The invention discloses a pipe curtain cover excavation reverse construction method for subway station construction. The method comprises the steps that firstly, a cover excavation mode is adopted forright line or left line excavation of a subway station; after a right line or left line of the subway station is subjected to cover excavation to a preset position, a pipe curtain is jacked from an excavation line to a non-excavation line to form a shed cover structure; soil below the shed cover structure is excavated out, and a working face is provided for a construction top plate; and then, a cover excavation reverse construction method is adopted, and all layers of plate beams of the station are sequentially constructed. According to the pipe curtain cover excavation reverse construction method, the supporting effect of a transverse pipe curtain structure is utilized, bearing of the dead load of soft soil of a water-rich sand layer above the transverse pipe curtain structure and the live load of traveling vehicles and pedestrians is achieved, meanwhile, effective avoiding of complex underground pipelines in overlying soil can be achieved, and inconvenience brought to pedestrian traffic due to the fact that the ground is excessively occupied is avoided.
本发明公开了一种用于地铁车站建造的管幕盖挖逆作施工方法,首先采用盖挖方式进行地铁车站右线或左线开挖;在地铁车站右线或左线盖挖至预定位置后,由开挖线向未开挖线顶进管幕形成棚盖结构;挖除棚盖结构下方土体,为施工顶板提供工作面;之后采用盖挖逆作施工方法,依次施工车站各层板梁;本发明利用横向管幕结构的支撑作用,实现了对横向管幕结构上方富水砂层软弱土体恒载及行车行人活载的承受,同时能够实现对上覆土体中复杂的地下管线的有效避让,避免了过度占用地面给行人交通带来的不便。
Pipe curtain cover excavation reverse construction method for subway station construction
The invention discloses a pipe curtain cover excavation reverse construction method for subway station construction. The method comprises the steps that firstly, a cover excavation mode is adopted forright line or left line excavation of a subway station; after a right line or left line of the subway station is subjected to cover excavation to a preset position, a pipe curtain is jacked from an excavation line to a non-excavation line to form a shed cover structure; soil below the shed cover structure is excavated out, and a working face is provided for a construction top plate; and then, a cover excavation reverse construction method is adopted, and all layers of plate beams of the station are sequentially constructed. According to the pipe curtain cover excavation reverse construction method, the supporting effect of a transverse pipe curtain structure is utilized, bearing of the dead load of soft soil of a water-rich sand layer above the transverse pipe curtain structure and the live load of traveling vehicles and pedestrians is achieved, meanwhile, effective avoiding of complex underground pipelines in overlying soil can be achieved, and inconvenience brought to pedestrian traffic due to the fact that the ground is excessively occupied is avoided.
本发明公开了一种用于地铁车站建造的管幕盖挖逆作施工方法,首先采用盖挖方式进行地铁车站右线或左线开挖;在地铁车站右线或左线盖挖至预定位置后,由开挖线向未开挖线顶进管幕形成棚盖结构;挖除棚盖结构下方土体,为施工顶板提供工作面;之后采用盖挖逆作施工方法,依次施工车站各层板梁;本发明利用横向管幕结构的支撑作用,实现了对横向管幕结构上方富水砂层软弱土体恒载及行车行人活载的承受,同时能够实现对上覆土体中复杂的地下管线的有效避让,避免了过度占用地面给行人交通带来的不便。
Pipe curtain cover excavation reverse construction method for subway station construction
一种用于地铁车站建造的管幕盖挖逆作施工方法
ZHOU QINGCAI (author) / WU HAO (author) / WANG NING (author) / ZHAO GUANGBO (author) / XIAO HONGLONG (author) / LI CHANGSHAN (author) / YANG FENFEN (author) / YANG XUEGANG (author) / XU HAIQIANG (author) / LIU BAO (author)
2020-06-09
Patent
Electronic Resource
Chinese
Construction method of cover excavation and underground excavation combined subway station structure
European Patent Office | 2023
|European Patent Office | 2024
|Subway station cover and excavation top-down structure and construction method
European Patent Office | 2023
|Subway station deep foundation pit excavation construction method
European Patent Office | 2015
|