Construction method of tall-and-big cone in silo
The embodiment of the invention discloses a construction method of a tall-and-big cone in a silo. Construction is carried out sequentially according to the following working steps of cone bottom formwork installation, and cone bottom formwork one-time formation; cone construction joint division; cone ring beam construction; rebar binding of a first construction segment of a cone; inner back shoreinstallation of the first construction segment of the cone; upper formwork installation of the first construction segment; concrete pouring; and construction of a second construction segment and a third construction segment, wherein according to the specific steps of the construction, a fourth step to a seventh step are repeated. According to the embodiment of the construction method of the tall-and-big cone in the silo, it is guaranteed that concrete of the cone is solid on the inside and smooth on the outside, safety of constructors is guaranteed, the construction period is shortened, and the construction cost is reduced.
本发明实施例公开一种筒仓内高大椎体施工方法,按照如下工序依次施工:椎体底部模板安装,椎体底模一次成型;椎体施工缝划分;椎体环梁施工;椎体第一施工段钢筋绑扎;椎体第一施工段安装内顶撑;第一施工段安装上部模板;混凝土浇筑;第二施工段、第三施工段施工,具体步骤为重复步骤四至步骤七;本发明实施例确保了椎体混凝土里实外光,保证了施工人员的安全,并缩短了施工工期,降低了施工成本。
Construction method of tall-and-big cone in silo
The embodiment of the invention discloses a construction method of a tall-and-big cone in a silo. Construction is carried out sequentially according to the following working steps of cone bottom formwork installation, and cone bottom formwork one-time formation; cone construction joint division; cone ring beam construction; rebar binding of a first construction segment of a cone; inner back shoreinstallation of the first construction segment of the cone; upper formwork installation of the first construction segment; concrete pouring; and construction of a second construction segment and a third construction segment, wherein according to the specific steps of the construction, a fourth step to a seventh step are repeated. According to the embodiment of the construction method of the tall-and-big cone in the silo, it is guaranteed that concrete of the cone is solid on the inside and smooth on the outside, safety of constructors is guaranteed, the construction period is shortened, and the construction cost is reduced.
本发明实施例公开一种筒仓内高大椎体施工方法,按照如下工序依次施工:椎体底部模板安装,椎体底模一次成型;椎体施工缝划分;椎体环梁施工;椎体第一施工段钢筋绑扎;椎体第一施工段安装内顶撑;第一施工段安装上部模板;混凝土浇筑;第二施工段、第三施工段施工,具体步骤为重复步骤四至步骤七;本发明实施例确保了椎体混凝土里实外光,保证了施工人员的安全,并缩短了施工工期,降低了施工成本。
Construction method of tall-and-big cone in silo
一种筒仓内高大椎体施工方法
TANG ZHONG (author) / SHANG XIUMIN (author) / ZHANG JINLIAN (author)
2020-07-17
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
European Patent Office | 2022
|Flat RP/PP sheets make tall round silo
Engineering Index Backfile | 1965
Design and Construction of Fly Ash Silo with Inverted Cone
British Library Online Contents | 2012
|Design and Construction of Fly Ash Silo with Inverted Cone
Online Contents | 2012
|Design and Construction of the World's Largest Inverted Cone Cement Silo
British Library Conference Proceedings | 1994
|