Large cutter suction dredger pile reversing system and method
The invention discloses a large cutter suction dredger pile reversing system and method, and relates to the technical field of cutter suction dredger construction. The system comprises a pile reversing system for a main steel pile and a pile reversing system for an auxiliary steel pile, the pile reversing system for the main steel pile comprises a main pile reversing clamp, a main steel pile maintaining clamp, a main balance oil cylinder, a main pile reversing oil cylinder, a main walking oil cylinder and a trolley, the main balance oil cylinder, the main pile reversing oil cylinder and the main walking oil cylinder are each provided with an oil cylinder base, the main pile reversing clamp and the main steel pile maintaining clamp are sequentially arranged on the surface of the main steelpile, the trolley is arranged below the main balance oil cylinder, and the main walking oil cylinder is arranged on the lower middle portion of the trolley. According to the pile reversing system andmethod for the large cutter suction dredger, the pile reversing system for the main steel pile and the auxiliary steel pile is created, the preparation work requirement before pile reversing is provided for pile reversing work, specific operation in the pile reversing process is clear, and safety inspection work after pile reversing is guaranteed.
本发明公开了一种大型绞吸式挖泥船倒桩系统及方法,涉及绞吸式挖泥船建造技术领域,包括用于主钢桩的倒桩系统以及用于辅钢桩的倒桩系统,所述用于主钢桩的倒桩系统包括主倒桩夹具、主钢桩保持夹具、主平衡油缸、主倒桩油缸、主行走油缸以及台车,所述主平衡油缸、主倒桩油缸以及主行走油缸均设置有油缸基座,所述主倒桩夹具、主钢桩保持夹具依次设置在主钢桩的表面上,所述台车设置在主平衡油缸的下方,所述主行走油缸设置在台车的中下部位置。该大型绞吸式挖泥船倒桩系统及方法,通过对主钢桩以及辅钢桩的倒桩系统进行创造,为倒桩工作提供倒桩前的准备工作要求,明确在倒桩过程中的具体操作,保证倒桩后的安全检查工作。
Large cutter suction dredger pile reversing system and method
The invention discloses a large cutter suction dredger pile reversing system and method, and relates to the technical field of cutter suction dredger construction. The system comprises a pile reversing system for a main steel pile and a pile reversing system for an auxiliary steel pile, the pile reversing system for the main steel pile comprises a main pile reversing clamp, a main steel pile maintaining clamp, a main balance oil cylinder, a main pile reversing oil cylinder, a main walking oil cylinder and a trolley, the main balance oil cylinder, the main pile reversing oil cylinder and the main walking oil cylinder are each provided with an oil cylinder base, the main pile reversing clamp and the main steel pile maintaining clamp are sequentially arranged on the surface of the main steelpile, the trolley is arranged below the main balance oil cylinder, and the main walking oil cylinder is arranged on the lower middle portion of the trolley. According to the pile reversing system andmethod for the large cutter suction dredger, the pile reversing system for the main steel pile and the auxiliary steel pile is created, the preparation work requirement before pile reversing is provided for pile reversing work, specific operation in the pile reversing process is clear, and safety inspection work after pile reversing is guaranteed.
本发明公开了一种大型绞吸式挖泥船倒桩系统及方法,涉及绞吸式挖泥船建造技术领域,包括用于主钢桩的倒桩系统以及用于辅钢桩的倒桩系统,所述用于主钢桩的倒桩系统包括主倒桩夹具、主钢桩保持夹具、主平衡油缸、主倒桩油缸、主行走油缸以及台车,所述主平衡油缸、主倒桩油缸以及主行走油缸均设置有油缸基座,所述主倒桩夹具、主钢桩保持夹具依次设置在主钢桩的表面上,所述台车设置在主平衡油缸的下方,所述主行走油缸设置在台车的中下部位置。该大型绞吸式挖泥船倒桩系统及方法,通过对主钢桩以及辅钢桩的倒桩系统进行创造,为倒桩工作提供倒桩前的准备工作要求,明确在倒桩过程中的具体操作,保证倒桩后的安全检查工作。
Large cutter suction dredger pile reversing system and method
一种大型绞吸式挖泥船倒桩系统及方法
LI ZHANPENG (author) / ZHOU XU (author)
2020-08-11
Patent
Electronic Resource
Chinese
European Patent Office | 2024
|British Library Online Contents | 1995
|POSITIONING STEEL PILE WELDING PROCESS OF CUTTER SUCTION DREDGER
European Patent Office | 2021
|