Expressway vacuum grouting process
The invention discloses an expressway vacuum grouting process which comprises the following steps: S1, manufacturing a prestressed concrete member, wherein the prestressed concrete member adopts a straight beam, bent beam and u-shaped beam combined rib distribution mode, and a plastic corrugated pipe is selected as a pipe used in the expressway vacuum grouting process; S2, preparing various materials, tools and equipment, ensuring enough quantity and intact quality, and ensuring normal supply of water and electric energy; S3, installing all the devices and parts are installed according to a construction drawing and connecting in sequence; S4, performing trial vacuumizing; S5, stirring the cement paste, pouring a certain amount of Portland cement, expansive cement, fly ash and water into astirrer, stirring for 2 minutes, pouring a certain amount of water reducing agent into the stirrer, and stirring for 3 minutes; and S6, grouting: specifically, a grouting valve is closed, a vacuum pump is started, when the vacuum degree reaches-0.07 MPa to-0.09 MPa, the vacuum pump is stopped, the grouting valve is opened, a grouting pump is started, and the stirred cement paste is conveyed to a grouting pipeline to be grouted.
本发明公开了一种高速公路真空灌浆工艺,包括以下步骤:S1:进行预应力混凝土构件的制作,预应力混凝土构件采用直束、弯曲和u型束组合的布筋方式,其中使用的管子选用塑料波纹管;S2、将各种材料、工具、设备准备好,确保数量足够,质量完好,并确保水电能正常供应;S3、按照施工图纸进行各设备、部件的安装,依次连接好;S4、试抽真空;S5、搅拌水泥浆,将一定量的硅酸盐水泥、膨胀水泥、粉煤灰和水倒入搅拌机中,搅拌2分钟后,将一定量的减水剂倒入搅拌机中搅拌3分钟;S6、灌浆:关闭灌浆阀,启动真空泵,当真空度达到‑0.07~‑0.09MPa时停止真空泵,打开灌浆阀,启动灌浆泵,将搅拌好的水泥浆输送至灌浆管道进行灌浆。
Expressway vacuum grouting process
The invention discloses an expressway vacuum grouting process which comprises the following steps: S1, manufacturing a prestressed concrete member, wherein the prestressed concrete member adopts a straight beam, bent beam and u-shaped beam combined rib distribution mode, and a plastic corrugated pipe is selected as a pipe used in the expressway vacuum grouting process; S2, preparing various materials, tools and equipment, ensuring enough quantity and intact quality, and ensuring normal supply of water and electric energy; S3, installing all the devices and parts are installed according to a construction drawing and connecting in sequence; S4, performing trial vacuumizing; S5, stirring the cement paste, pouring a certain amount of Portland cement, expansive cement, fly ash and water into astirrer, stirring for 2 minutes, pouring a certain amount of water reducing agent into the stirrer, and stirring for 3 minutes; and S6, grouting: specifically, a grouting valve is closed, a vacuum pump is started, when the vacuum degree reaches-0.07 MPa to-0.09 MPa, the vacuum pump is stopped, the grouting valve is opened, a grouting pump is started, and the stirred cement paste is conveyed to a grouting pipeline to be grouted.
本发明公开了一种高速公路真空灌浆工艺,包括以下步骤:S1:进行预应力混凝土构件的制作,预应力混凝土构件采用直束、弯曲和u型束组合的布筋方式,其中使用的管子选用塑料波纹管;S2、将各种材料、工具、设备准备好,确保数量足够,质量完好,并确保水电能正常供应;S3、按照施工图纸进行各设备、部件的安装,依次连接好;S4、试抽真空;S5、搅拌水泥浆,将一定量的硅酸盐水泥、膨胀水泥、粉煤灰和水倒入搅拌机中,搅拌2分钟后,将一定量的减水剂倒入搅拌机中搅拌3分钟;S6、灌浆:关闭灌浆阀,启动真空泵,当真空度达到‑0.07~‑0.09MPa时停止真空泵,打开灌浆阀,启动灌浆泵,将搅拌好的水泥浆输送至灌浆管道进行灌浆。
Expressway vacuum grouting process
一种高速公路真空灌浆工艺
ZENG FANCHUN (author) / YU JINHAI (author) / ZHOU YIBO (author) / CHEN HUAXING (author)
2020-08-28
Patent
Electronic Resource
Chinese
IPC:
C04B
Kalk
,
LIME
Geopolymer grouting construction process and equipment for repairing expressway
European Patent Office | 2021
|High-pressure jet grouting pile construction technological process for expressway construction
European Patent Office | 2024
|Chemical grouting applied to widen Tokyo Metropolitan Expressway
British Library Conference Proceedings | 1996
|