A platform for research: civil engineering, architecture and urbanism
Road construction method
The invention relates to a road construction method which comprises a preparation step: leveling a pavement to be constructed, forming a roadbed, carrying out construction lofting at the top of the roadbed, prefabricating an asphalt pavement in a factory, and transporting the prefabricated asphalt pavement to a construction road section. To be specific, the method comprises the following steps: S1, laying a waterproof cushion layer on a roadbed; S2, laying a thick slag cushion layer on the cushion layer; S3, laying a 4% cement stabilized macadam lower base layer on the thick slag cushion layer; S4, laying a cement stabilized macadam connecting layer on the 4% cement stabilized macadam lower base layer; S5, hoisting the asphalt pavement, and placing the asphalt pavement on the cement stabilized macadam connecting layer; S6, arranging connecting assemblies on the two opposite sides of the asphalt pavement; S7, connecting the connecting assemblies between the two asphalt pavements; and S8, laying a covering assembly on the tops of every two adjacent asphalt pavement connecting assemblies. The method has the effects that the road construction period is shortened, and the enterprise benefit is improved to a certain extent.
本发明涉及一种道路施工方法,包括以下步骤:准备步骤:平整待施工路面,形成路基,于路基的顶部进行施工放样,将沥青路面于工厂进行预制,并且将预制后的沥青路面运输至施工路段。S1:在路基上铺设防水垫层;S2:在垫层上铺设厚宕渣垫层;S3:在厚宕渣垫层上铺设4%水泥稳定碎石下基层;S4:在4%水泥稳定碎石下基层上铺设水泥稳定碎石连接层;S5:吊装沥青路面,并且将沥青路面放置在水泥稳定碎石连接层上;S6:于所述沥青路面相对的两侧设置连接组件;S7:将两沥青路面之间的连接组件进行连接;S8:于相邻两沥青路面连接组件的顶部铺设盖合组件。本发明具有缩短了道路施工周期,在一定程度上提升了企业效益的效果。
Road construction method
The invention relates to a road construction method which comprises a preparation step: leveling a pavement to be constructed, forming a roadbed, carrying out construction lofting at the top of the roadbed, prefabricating an asphalt pavement in a factory, and transporting the prefabricated asphalt pavement to a construction road section. To be specific, the method comprises the following steps: S1, laying a waterproof cushion layer on a roadbed; S2, laying a thick slag cushion layer on the cushion layer; S3, laying a 4% cement stabilized macadam lower base layer on the thick slag cushion layer; S4, laying a cement stabilized macadam connecting layer on the 4% cement stabilized macadam lower base layer; S5, hoisting the asphalt pavement, and placing the asphalt pavement on the cement stabilized macadam connecting layer; S6, arranging connecting assemblies on the two opposite sides of the asphalt pavement; S7, connecting the connecting assemblies between the two asphalt pavements; and S8, laying a covering assembly on the tops of every two adjacent asphalt pavement connecting assemblies. The method has the effects that the road construction period is shortened, and the enterprise benefit is improved to a certain extent.
本发明涉及一种道路施工方法,包括以下步骤:准备步骤:平整待施工路面,形成路基,于路基的顶部进行施工放样,将沥青路面于工厂进行预制,并且将预制后的沥青路面运输至施工路段。S1:在路基上铺设防水垫层;S2:在垫层上铺设厚宕渣垫层;S3:在厚宕渣垫层上铺设4%水泥稳定碎石下基层;S4:在4%水泥稳定碎石下基层上铺设水泥稳定碎石连接层;S5:吊装沥青路面,并且将沥青路面放置在水泥稳定碎石连接层上;S6:于所述沥青路面相对的两侧设置连接组件;S7:将两沥青路面之间的连接组件进行连接;S8:于相邻两沥青路面连接组件的顶部铺设盖合组件。本发明具有缩短了道路施工周期,在一定程度上提升了企业效益的效果。
Road construction method
一种道路施工方法
LI JIANKANG (author) / QIAN LIANG (author) / YU YEJUN (author) / HU XIONGLIANG (author) / CHEN FUXIANG (author) / HE XIANSHEN (author) / SHANG KUNPENG (author) / CHEN SHIWEN (author)
2020-09-18
Patent
Electronic Resource
Chinese
IPC:
E01C
Bau von Straßen, Sportplätzen oder dgl., Decken dafür
,
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE
ROAD CONSTRUCTION MATERIAL, ROAD CONSTRUCTION MATERIAL SET, AND ROAD CONSTRUCTION METHOD
European Patent Office | 2024
|